Liberty
University BUSI 411 exam 2 solutions answers right
How
many versions: 13 different versions
Question 1 Sensitivity analysis is required
because:
Question 2 The operations manager for a
welldrilling company must recommend whether to build a new facility, expand
his existing one, or do nothing. He estimates that longrun profits (in $000)
will vary with the amount of precipitation (rainfall) as follows: If he uses
the maximax criterion, which alternative will he decide to select?
Question 3 The owner of Firewood To Go is
considering buying a hydraulic wood splitter which sells for $50,000. He
figures it will cost an additional $100 per cord to purchase and split wood
with this machine, while he can sell each cord of split wood for $125. What
would the potential profit be if he were to split 4,000 cords of wood with this
machine?
Question 4 One local hospital has just
enough space and funds currently available to start either a cancer or heart
research lab. If administration decides on the cancer lab, there is a 20
percent chance of getting $100,000 in outside funding from the American Cancer
Society next year, and an 80 percent chance of getting nothing. If the cancer
research lab is funded the first year, no additional outside funding will be
available the second year. However, if it is not funded the first year, then
management estimates the chances are 50 percent it will get $100,000 the
following year, and 50 percent that it will get nothing again. If, however, the
hospital's management decides to go with the heart lab, then there is a 50
percent chance of getting $50,000 in outside funding from the American Heart
Association the first year and a 50 percent change of getting nothing. If the
heart lab is funded the first year, management estimates a 40 percent chance of
getting another $50,000 and a 60 percent chance of getting nothing additional
the second year. If it is not funded the first year, then management estimates
a 60 percent chance for getting $50,000 and a 40 percent chance for getting
nothing in the following year. For both the cancer and heart research labs, no
further possible funding is anticipated beyond the first two years. What is the
expected value for the decision alternative to select the cancer lab?
Question 5 Consider the following decision
scenario: *PV for profits ($000) If P(high) is .60, the choice for maximum expected
value would be:
Question 6 Daily capacity of a product
layout is determined by:
Question 7 The type of processing system
which is used for highly standardized products is:
Question 8 Product profiling links key
product or service requirements to:
Question 9 A company needs to locate three
departments (X, Y, and Z) in the three areas (I, II, and III) of a new
facility. They want to minimize interdepartmental transportation costs, which
are expected to be $.50 per load meter moved. An analyst has prepared the
following flow and distance matrices: What is the layout that will minimize the
total distance loads will be moved each week?
Question 10 In which type of processing
system would gasoline be produced from crude oil?
Question 11 Suppose the first unit of
output required 900 labor hours, and the second unit required only 810. At this
rate, how many more units must be produced before labor requirements are less
than 700 hours?
Question 12 A manager wants to analyze the
learning curve associated with producing one of his company's products.
Accordingly, he has gathered the following data: What is the learning curve
percentage?
Question 13 The owner of Kat Motel wants to
develop a time standard for the task of cleaning a cat cage. In a preliminary
study, she observed one of her workers perform this task six times, with the
following results: How many observations should be made if she wants to be
95.44 percent confident that the maximum error in the observed time is two
seconds? Assume that the standard deviation of the task time is six seconds.
Question 14 A manager wants to analyze the
learning curve associated with producing one of his company's products.
Accordingly, he has gathered the following data: Approximately how long will it
take to produce the fifth through tenth units?
Question 15 Determining the number of
cycles to observe is an element of:
Question 16 Which of the following is least
important as a consideration for a firm at the beginning of a supply chain?
Question 17 Suppose a decision maker is
confronted with the following transportation model scenario: What is the total
cost of the optimal solution?
Question 18 For service firms such as banks
and supermarkets, location decisions are critical elements of __________
strategy.
Question 19 Which of the following is the
last step in the procedure for making location decisions?
Question 20 The Skulls, a student social
organization, has two different locations under consideration for constructing
a new chapter house. The Skulls' president, a POM student, estimates that due
to differing land costs, utility rates, etc., both fixed and variable costs
would be different for each of the proposed sites, as follows: What would be
the total annual costs for the Alpha Ave. location with 20 persons living
there?
Question 21 The breakeven quantity can be
determined by dividing the fixed costs by the difference between the revenue
per unit and the variable cost per unit.
Question 22 A cafeteria line would be an
example of a processfocused layout.
Question 23 Ergonomics is an important part
of job design to consider when we automate the system.
Question 24 For service organizations, the
dominant factors in location analysis usually are marketrelated.
Question 25 A strategy that emphasizes
convenience for the customers would probably select a single very large
facility.
1. Decision
trees, with their predetermined analysis of a situation, are really not useful
in making health care decisions since every person is unique.
True False
True False
2. Bounded rationality refers to the limits imposed on
decision-making because of costs, human abilities, time, technology, and/or
availability of information.
True False
True False
3. In reaching a decision, the alternative with the
lowest cost should be ranked #1.
True False
True False
4. The expected monetary value approach is most
appropriate when the decision-maker is risk-neutral.
True False
True False
5. The value of perfect information is inversely
related to losses predicted.
True False
True False
6. Expected monetary value gives the long-run average
payoff if a large number of identical decisions could be made.
True False
True False
7. Among decision environments, risk implies that
certain parameters have probabilistic outcomes.
True False
True False
8. Among decision environments, uncertainty implies
that states of nature have wide ranging probabilities associated with
them.
True False
True False
9. In decision theory, states of nature refer to
possible future conditions.
True False
True False
10. The maximin approach involves choosing the
alternative with the highest payoff.
True False
True False
11. The maximin approach involves choosing the
alternative that has the "best worst" payoff.
True False
True False
12. The Laplace criterion treats states of nature as
being equally likely.
True False
True False
13. The maximax approach is a pessimistic
strategy.
True False
True False
14. A weakness of the maximin approach is that it
loses some information.
True False
True False
15. The expected value approach applies to
decision-making under uncertainty.
True False
True False
16. The expected value approach is used for
decision-making under risk.
True False
True False
17. The EVPI indicates an upper limit on the amount a
decision-maker should be willing to spend to obtain additional
information.
True False
True False
18. Graphical sensitivity analysis is limited to cases
with no more than two alternatives.
True False
True False
19. Graphical sensitivity analysis is used for
decision-making under risk.
True False
True False
20. An advantage of decision trees compared to payoff
tables is that they permit us to analyze situations involving sequential
decisions.
True False
True False
21. The term sub-optimization is best described as
the:
A. result of individual departments making the best decisions for their own areas
B. limitations on decision-making caused by costs and time
C. result of failure to adhere to the steps in the decision process
D. result of ignoring symptoms of the problem
E. none of the above
A. result of individual departments making the best decisions for their own areas
B. limitations on decision-making caused by costs and time
C. result of failure to adhere to the steps in the decision process
D. result of ignoring symptoms of the problem
E. none of the above
22. Which phrase best describes the term bounded
rationality?
A. thinking a problem through clearly before acting
B. taking care not to exhaust limited resources
C. the result of departmentalized decision making
D. limits imposed on decision making by costs, time, and technology
E. the use of extremely structured steps in the decision making process
A. thinking a problem through clearly before acting
B. taking care not to exhaust limited resources
C. the result of departmentalized decision making
D. limits imposed on decision making by costs, time, and technology
E. the use of extremely structured steps in the decision making process
23. Testing how a problem solution reacts to changes
in one or more of the model parameters is called:
A. simulation
B. sensitivity analysis
C. priority recognition
D. analysis of variance
E. decision analysis
A. simulation
B. sensitivity analysis
C. priority recognition
D. analysis of variance
E. decision analysis
24. Sensitivity analysis is required because
_______.
A. payoffs and probabilities are estimates
B. most decision will affect employees
C. expected payoffs are sensitive to the time value of money
D. it's the second step in the decision model
E. with the passage of time, small decisions get bigger
A. payoffs and probabilities are estimates
B. most decision will affect employees
C. expected payoffs are sensitive to the time value of money
D. it's the second step in the decision model
E. with the passage of time, small decisions get bigger
25. A tabular presentation that shows the outcome for
each decision alternative under the various possible states of nature is called
a/an:
A. payoff table
B. feasible region
C. Laplace table
D. decision tree
E. payback period matrix
A. payoff table
B. feasible region
C. Laplace table
D. decision tree
E. payback period matrix
26. Which of the following characterizes
decision-making under uncertainty?
A. Decision-makers must rely on probabilities in assessing outcomes.
B. The likelihood of possible future events is unknown.
C. Relevant parameters have known values.
D. Certain parameters have probabilistic outcomes.
E. none of the above
A. Decision-makers must rely on probabilities in assessing outcomes.
B. The likelihood of possible future events is unknown.
C. Relevant parameters have known values.
D. Certain parameters have probabilistic outcomes.
E. none of the above
27. Which of the following is not an approach
for decision-making under uncertainty?
A. decision trees
B. maximin
C. maximax
D. minimax regret
E. Laplace
A. decision trees
B. maximin
C. maximax
D. minimax regret
E. Laplace
28. Determining the worst payoff for each alternative
and choosing the alternative with the "best worst" is the approach
called:
A. minimin
B. maximin
C. maximax
D. minimax regret
E. Laplace
A. minimin
B. maximin
C. maximax
D. minimax regret
E. Laplace
29. Determining the average payoff for each
alternative and choosing the alternative with the highest average is the
approach called:
A. minimin
B. maximin
C. maximax
D. minimax regret
E. Laplace
A. minimin
B. maximin
C. maximax
D. minimax regret
E. Laplace
30. The maximin approach to decision-making refers
to:
A. minimizing the maximum return
B. maximizing the minimum return
C. maximizing the minimum expected value
D. choosing the alternative with the highest payoff
E. choosing the alternative with the minimum payoff
A. minimizing the maximum return
B. maximizing the minimum return
C. maximizing the minimum expected value
D. choosing the alternative with the highest payoff
E. choosing the alternative with the minimum payoff
31. Which one of these is not used in decision-making
under risk?
A. EVPI
B. EMV
C. decision trees
D. minimax regret
E. All are used for risk situations.
A. EVPI
B. EMV
C. decision trees
D. minimax regret
E. All are used for risk situations.
32. The term opportunity loss or regret is most
closely associated with:
A. minimax regret
B. maximax
C. maximin
D. expected monetary value
E. Laplace
A. minimax regret
B. maximax
C. maximin
D. expected monetary value
E. Laplace
33. The expected monetary value criterion (EMV) is the
decision-making approach used with the decision environment of:
A. certainty
B. risk
C. uncertainty
D. all of the above
E. none of the above
A. certainty
B. risk
C. uncertainty
D. all of the above
E. none of the above
34. A decision tree is:
A. an algebraic representation of alternatives
B. a behavioral representation of alternatives
C. a matrix representation of alternatives
D. a schematic representation of alternatives
E. limited to a maximum of 12 branches
A. an algebraic representation of alternatives
B. a behavioral representation of alternatives
C. a matrix representation of alternatives
D. a schematic representation of alternatives
E. limited to a maximum of 12 branches
35. The difference between expected payoff under
certainty and expected payoff under risk is the expected:
A. monetary value
B. value of perfect information
C. net present value
D. rate of return
E. profit
A. monetary value
B. value of perfect information
C. net present value
D. rate of return
E. profit
36. If the minimum expected regret is computed, it
indicates to a decision-maker the expected:
A. value of perfect information
B. payoff under certainty
C. monetary value
D. payoff under risk
E. none of the above
A. value of perfect information
B. payoff under certainty
C. monetary value
D. payoff under risk
E. none of the above
37. The term sensitivity analysis is most closely
associated with:
A. maximax
B. maximin
C. decision-making under risk
D. minimax regret
E. Laplace criterion
A. maximax
B. maximin
C. decision-making under risk
D. minimax regret
E. Laplace criterion
38. A manager has developed the following payoff table
that indicates the profits associated with a set of alternatives under two
possible states of nature.
Answer the following questions:
(A) If the manager uses maximin as the decision criterion, which of the alternatives would be indicated?
(B) If the manager uses minimax regret as the criterion, which alternative would be indicated?
(C) Determine the expected value of perfect information if P(S2) = .40.
(D) Determine the range of P(S2) for which each alternative would be optimal.
Answer the following questions:
(A) If the manager uses maximin as the decision criterion, which of the alternatives would be indicated?
(B) If the manager uses minimax regret as the criterion, which alternative would be indicated?
(C) Determine the expected value of perfect information if P(S2) = .40.
(D) Determine the range of P(S2) for which each alternative would be optimal.
39. A
manager's staff has compiled the information below which pertains to four
capacity alternatives under four states of nature. Values in the matrix are
present value in thousands of dollars.
(A) Assuming a maximax strategy, which alternative would be chosen?
(B) If maximin were used, which alternative would be chosen?
(C) If states of nature are equally likely and an expected value criterion of maximization is used, which alternative would be chosen?
(A) Assuming a maximax strategy, which alternative would be chosen?
(B) If maximin were used, which alternative would be chosen?
(C) If states of nature are equally likely and an expected value criterion of maximization is used, which alternative would be chosen?
40. A
manager has learned that annual profits from four alternatives being considered
for solving a capacity problem are projected to be $15,000 for A, $30,000 for
B, $45,000 for C, and $60,000 for D if state of nature 1 occurs; and $60,000
for A, $80,000 for B, $90,000 for C, and $35,000 for D if state of nature 2
occurs.
(A) Assuming maximax is used, what alternative would be chosen?
(B) Assuming maximin is used, what alternative would be chosen?
(C) If P(State of Nature 1) is .40, what alternative has the highest expected monetary value?
(D) Determine the range of P(S2) for which each alternative would be optimal.
(A) Assuming maximax is used, what alternative would be chosen?
(B) Assuming maximin is used, what alternative would be chosen?
(C) If P(State of Nature 1) is .40, what alternative has the highest expected monetary value?
(D) Determine the range of P(S2) for which each alternative would be optimal.
41. A
manager is quite concerned about the recent deterioration of a section of the
roof on a building that houses her firm's computer operations. According to her
assistant there are three options which merit consideration: A, B, and C.
Moreover, there are three possible future conditions that must be included in
the analysis: I, which has a probability of occurrence of .5; II, which has a
probability of .3; and III, which has a probability of .2.
If condition I materializes, A will cost $12,000, B will cost $20,000, and C will cost $16,000. If condition II materializes, the costs will be $15,000 for A, $18,000 for B, and $14,000 for C. If condition III materializes, the costs will be $10,000 for A, $15,000 for B, and $19,000 for C.
(A) Draw a decision tree for this problem.
(B) Using expected monetary value, which alternative should be chosen?
If condition I materializes, A will cost $12,000, B will cost $20,000, and C will cost $16,000. If condition II materializes, the costs will be $15,000 for A, $18,000 for B, and $14,000 for C. If condition III materializes, the costs will be $10,000 for A, $15,000 for B, and $19,000 for C.
(A) Draw a decision tree for this problem.
(B) Using expected monetary value, which alternative should be chosen?
*PV for profits ($000)
42. The maximax strategy would be:
A. buy
B. lease
C. rent
D. high
E. low
A. buy
B. lease
C. rent
D. high
E. low
43. The maximin strategy would be:
A. buy
B. lease
C. rent
D. high
E. low
A. buy
B. lease
C. rent
D. high
E. low
44. The minimax regret strategy would be:
A. buy
B. lease
C. rent
D. high
E. low
A. buy
B. lease
C. rent
D. high
E. low
45. If P(high) is .60, the choice for maximum expected
value would be:
A. buy
B. lease
C. rent
D. high
E. low
A. buy
B. lease
C. rent
D. high
E. low
*PV for profits ($000)
46. The maximax strategy would be:
A. small
B. Medium
C. med.-large
D. large
E. ex-large
A. small
B. Medium
C. med.-large
D. large
E. ex-large
47. The maximin strategy would be:
A. small
B. Medium
C. med.-large
D. large
E. ex-large
A. small
B. Medium
C. med.-large
D. large
E. ex-large
48. The minimax regret strategy would be:
A. small
B. Medium
C. med.-large
D. large
E. ex-large
A. small
B. Medium
C. med.-large
D. large
E. ex-large
49. If yes and no are equally likely, which
alternative has the largest expected monetary value?
A. small
B. Medium
C. med.-large
D. large
E. ex-large
A. small
B. Medium
C. med.-large
D. large
E. ex-large
*PV for profits ($000)
50. The maximax strategy would be:
A. A
B. B
C. C
D. D
E. E
A. A
B. B
C. C
D. D
E. E
51. The maximin strategy would be:
A. A
B. B
C. C
D. D
E. E
A. A
B. B
C. C
D. D
E. E
52. The minimax regret strategy would be:
A. A
B. B
C. C
D. D
E. E
A. A
B. B
C. C
D. D
E. E
53. With equally likely states of nature, the
alternative that has the largest expected monetary value is:
A. A
B. B
C. C
D. D
E. E
A. A
B. B
C. C
D. D
E. E
The new owner of a beauty shop is trying to decide
whether to hire one, two, or three beauticians. She estimates that profits next
year (in thousands of dollars) will vary with demand for her services and has
estimated demand in three categories low, medium and high
54. If she uses the maximax criterion, how many
beauticians will she decide to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
55. If she uses the Laplace criterion, how many
beauticians will she decide to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
56. If she uses the minimax regret criterion, how many
beauticians will she decide to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
57. If she feels the chances of low, medium, and high
demand are 50%, 20%, and 30% respectively, what are the expected annual profits
for the number of beauticians she will decide to hire?
A. $54,000
B. $55,000
C. $70,000
D. $80,000
E. $135,000
A. $54,000
B. $55,000
C. $70,000
D. $80,000
E. $135,000
58. If she feels the chances of low, medium, and high
demand are 50%, 20%, and 30% respectively, what is her expected value of
perfect information?
A. $54,000
B. $55,000
C. $70,000
D. $80,000
E. $135,000
A. $54,000
B. $55,000
C. $70,000
D. $80,000
E. $135,000
The operations manager for a local bus company wants
to decide whether he should purchase a small, medium, or large new bus for his
company. He estimates that the annual profits (in $000) will vary depending
upon whether passenger demand is low, moderate, or high, as follows:
59. If he uses the maximin criterion, which size bus
will he decide to purchase?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
60. If he uses the Laplace criterion, which size bus
will he decide to purchase?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
61. If he uses the minimax regret criterion, which
size bus will he decide to purchase?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
62. If he feels the chances of low, moderate, and high
demand are 30%, 30%, and 40% respectively, what is the expected annual profit
for the bus that he will decide to purchase?
A. $15,000
B. $61,000
C. $69,000
D. $72,000
E. $87,000
A. $15,000
B. $61,000
C. $69,000
D. $72,000
E. $87,000
63. If he feels the chances of low, moderate, and high
demand are 30%, 30%, and 40% respectively, what is his expected value of
perfect information?
A. $15,000
B. $61,000
C. $69,000
D. $72,000
E. $87,000
A. $15,000
B. $61,000
C. $69,000
D. $72,000
E. $87,000
The operations manager for a well-drilling company
must recommend whether to build a new facility, expand his existing one, or do
nothing. He estimates that long-run profits (in $000) will vary with the amount
of precipitation (rainfall) as follows:
64. If he uses the maximax criterion, which
alternative will he decide to select?
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
65. If he uses the Laplace criterion, which
alternative will he decide to select?
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
66. If he uses the minimax regret criterion, which
alternative will he decide to select?
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
A. do nothing
B. expand
C. build new
D. either do nothing or expand
E. either expand or build new
67. If he feels the chances of low, normal, and high
precipitation are 30%, 20%, and 50% respectively, what are expected long-run
profits for the alternative he will select?
A. $140,000
B. $170,000
C. $285,000
D. $305,000
E. $475,000
A. $140,000
B. $170,000
C. $285,000
D. $305,000
E. $475,000
68. If he feels the chances of low, normal, and high
precipitation are 30%, 20%, and 50% respectively, what is his expected value of
perfect information?
A. $140,000
B. $170,000
C. $285,000
D. $305,000
E. $475,000
A. $140,000
B. $170,000
C. $285,000
D. $305,000
E. $475,000
The local operations manager for the Internal Revenue
Service must decide whether to hire one, two, or three temporary tax examiners
for the upcoming tax season. She estimates that net revenues (in thousands of
dollars) will vary with how well taxpayers comply with the new tax code just
passed by Congress, as follows:
69. If she uses the maximin criterion, how many new
examiners will she decide to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
70. If she uses the Laplace criterion, how many new
examiners will she decide to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
71. If
she uses the minimax regret criterion, how many new examiners will she decide
to hire?
A. one
B. two
C. three
D. either one or two
E. either two or three
A. one
B. two
C. three
D. either one or two
E. either two or three
72. If she feels the chances of low, medium, and high
compliance are 20%, 30%, and 50% respectively, what are the expected net
revenues for the number of assistants she will decide to hire?
A. $26,000
B. $46,000
C. $48,000
D. $50,000
E. $76,000
A. $26,000
B. $46,000
C. $48,000
D. $50,000
E. $76,000
73. If she feels the chances of low, medium, and high
compliance are 20%, 30%, and 50% respectively, what is her expected value of
perfect information?
A. $16,000
B. $26,000
C. $46,000
D. $48,000
E. $50,000
A. $16,000
B. $26,000
C. $46,000
D. $48,000
E. $50,000
The construction manager for Acme Construction, Inc.
must decide whether to build single-family homes, apartments, or condominiums.
He estimates annual profits (in $000) will vary with the population trend as
follows:
74. If he uses the maximin criterion, which kind of
dwellings will he decide to build?
A. single family
B. apartments
C. condominiums
D. either single family or apartments
E. either apartments or condos
A. single family
B. apartments
C. condominiums
D. either single family or apartments
E. either apartments or condos
75. If he uses the Laplace criterion, which kind of
dwellings will he decide to build?
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
76. If he uses the minimax regret criterion, which kind
of dwellings will he decide to build?
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
77. If he feels the chances of declining, stable, and
growing population trends are 40%, 50%, and 10%, respectively, which kind of
houses will he decide to build?
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
A. single family
B. apartments
C. condos
D. either single family or apartments
E. either apartments or condos
78. If he feels the chances of declining, stable, and
growing population trends are 40%, 50%, and 10%, respectively, what is his
expected value of perfect information?
A. $187,000
B. $132,000
C. $123,000
D. $65,000
E. $55,000
A. $187,000
B. $132,000
C. $123,000
D. $65,000
E. $55,000
The owner of Tastee Cookies needs to decide whether
to lease a small, medium, or large new retail outlet. She estimates that
monthly profits will vary with demand for her cookies as follows:
79. If she uses the maximax criterion, what size
outlet will she decide to lease?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
80. If she uses the maximin criterion, what size
outlet will she decide to lease?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
81. If she uses the Laplace criterion, what size
outlet will she decide to lease?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
82. If she uses the minimax regret criterion, what
size outlet will she decide to lease?
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
A. small
B. Medium
C. large
D. either small or Medium
E. either medium or large
83. If she feels there is a 30% chance that demand
will be high, what are the expected monthly profits for the outlet she will
decide to lease?
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
84. If she feels there is a 30% chance that demand
will be high, what is her expected payoff under certainty?
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
85. If she feels there is a 30% chance that demand
will be high, what is her expected value of perfect information?
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
A. $1,600
B. $1,100
C. $1,000
D. $900
E. $500
86. For what range of probability that demand will be
high, will she decide to lease the small facility?
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
87. For what range of probability that demand will be
high, will she decide to lease the medium facility?
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
88. For what range of probability that demand will be
high, will she decide to lease the large facility?
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
A. 0 - .25
B. 0 - .33
C. .25 - .5
D. .33 - 1
E. .5 - 1
The advertising manager for Roadside Restaurants,
Inc. needs to decide whether to spend this month's budget for advertising on
print media, television, or a mixture of the two. She estimates that the cost
per thousand "hits" (readers or viewers) will vary depending upon the
success of the new cable television network she plans to use, as follows:
89. If she uses the maximax criterion, which
advertising strategy will she use?
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
90. If she uses the maximin criterion, which
advertising strategy will she use?
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
91. If she uses the Laplace criterion, which
advertising strategy will she use?
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
92. If she uses the minimax regret criterion, which
advertising strategy will she use?
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
A. print
B. mixed
C. television
D. either print or mixed
E. either mixed or television
93. If she feels that there is a 60% chance that the
new cable network will be successful, what is her expected cost (per thousand
"hits") for the strategy she will select?
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
94. If she feels that there is a 60% chance that the
new cable network will be successful, what is her expected cost (per thousand
"hits") under certainty?
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
95. If she feels that there is a 60% chance that the
new cable network will be successful, what is her expected value (per thousand
"hits") of perfect information?
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
A. $3.40
B. $4.60
C. $8.00
D. $9.00
E. $10.00
96. For what range of probability that the new cable
network will be successful will she select the print media strategy?
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
97. For what range of probability that the new cable
network will be successful will she select the mixed media strategy?
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
98. For what range of probability that the new cable
network will be successful will she select the television media strategy?
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
A. 0 - .4
B. 0 - .55
C. .4 - .7
D. .55 - 1
E. .7 - 1
The head of operations for a movie studio wants to
determine which of two new scripts they should select for their next major
production. (Due to budgeting constraints, only one new picture can be
undertaken at this time.) She feels that script #1 has a 70 percent chance of
earning about $10,000,000 over the long run, but a 30 percent chance of losing
$2,000,000. If this movie is successful, then a sequel could also be produced,
with an 80 percent chance of earning $5,000,000, but a 20 percent chance of
losing $1,000,000. On the other hand, she feels that script #2 has a 60 percent
chance of earning $12,000,000, but a 40 percent chance of losing $3,000,000. If
successful, its sequel would have a 50 percent chance of earning $8,000,000,
but a 50 percent chance of losing $4,000,000. Of course, in either case, if the
original movie were a "flop," then no sequel would be produced.
99. What would be the total payoff if script #1 were a
success, but its sequel were not?
A. $15,000,000
B. $10,000,000
C. $9,000,000
D. $5,000,000
E. $-1,000,000
A. $15,000,000
B. $10,000,000
C. $9,000,000
D. $5,000,000
E. $-1,000,000
100. What is the probability that script #1 will be a
success, but its sequel will not?
A. .8
B. .7
C. .56
D. .2
E. .14
A. .8
B. .7
C. .56
D. .2
E. .14
101. What is the expected value of selecting script
#1?
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
102. What is the expected value of selecting script
#2?
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
103. What is the expected value for the optimum
decision alternative?
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
A. $15,000,000
B. $9,060,000
C. $8,400,000
D. $7,200,000
E. $6,000,000
One local hospital has just enough space and funds
presently available to start either a cancer or heart research lab. If
administration decides on the cancer lab, there is a 20 percent chance of
getting $100,000 in outside funding from the American Cancer Society next year,
and an 80 percent chance of getting nothing. If the cancer research lab is
funded the first year, no additional outside funding will be available the
second year. However, if it is not funded the first year, then management
estimates the chances are 50 percent it will get $100,000 the following year,
and 50 percent that it will get nothing again. If, however, Merciless's
management decides to go with the heart lab, then there's a 50 percent chance
of getting $50,000 in outside funding from the American Heart Association the
first year and a 50 percent change of getting nothing. If the heart lab is
funded the first year, management estimates a 40 percent chance of getting
another $50,000 and a 60 percent chance of getting nothing additional the
second year. If it is not funded the first year, then management estimates a 60
percent chance for getting $50,000 and a 40 percent chance for getting nothing
in the following year. For both the cancer and heart research labs, no further
possible funding is anticipated beyond the first two years.
104. What would be the total payoff if the heart lab
were funded in both the first and second years?
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
105. What is the probability that the heart lab will
be funded in both the first and second years?
A. .4
B. .3
C. .2
D. .1
E. 0
A. .4
B. .3
C. .2
D. .1
E. 0
106. What is the expected value for the decision
alternative to select the cancer lab?
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
107. What is the expected value for the decision
alternative to select the heart lab?
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
108. What is the expected value for the optimum
decision alternative?
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
A. $100,000
B. $60,000
C. $50,000
D. $40,000
E. $20,000
Two professors at a nearby university want to
co-author a new textbook in either economics or statistics. They feel that if
they write an economics book, they have a 50 percent chance of placing it with
a major publisher, and it should ultimately sell about 40,000 copies. If they
can't get a major publisher to take it, then they feel they have an 80 percent
chance of placing it with a smaller publisher, with ultimate sales of 30,000
copies. On the other hand, if they write a statistics book, they feel they have
a 40 percent chance of placing it with a major publisher, and it should result
in ultimate sales of about 50,000 copies. If they can't get a major publisher
to take it, they feel they have a 50 percent chance of placing it with a
smaller publisher, with ultimate sales of 35,000 copies.
109. What is the probability that the economics book
would wind up being placed with a smaller publisher?
A. .8
B. .5
C. .4
D. .2
E. .1
A. .8
B. .5
C. .4
D. .2
E. .1
110. What is the probability that the statistics book
would wind up being placed with a smaller publisher?
A. .6
B. .5
C. .4
D. .3
E. 0
A. .6
B. .5
C. .4
D. .3
E. 0
111. What is the expected value for the decision
alternative to write the economics book?
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
112. What is the expected value for the decision
alternative to write the statistics book?
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
113. What is the expected value for the optimum
decision alternative?
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
A. 50,000 copies
B. 40,000 copies
C. 32,000 copies
D. 30,500 copies
E. 10,500 copies
114. When a decision-making scenario involves two or
more departments, if the individual departments pursue what is optimal for
them, sometimes the overall organization suffers. This is an example of
_____________.
A. subminimization
B. suboptimization
C. rational boundaries
D. decision making under risk
E. decision making under uncertainty
A. subminimization
B. suboptimization
C. rational boundaries
D. decision making under risk
E. decision making under uncertainty
115. Which of the following is not a stage in the
decision making process?
A. select the best alternative
B. develop suitable alternatives
C. analyze and compare alternatives
D. monitor the competition
E. specify objectives
A. select the best alternative
B. develop suitable alternatives
C. analyze and compare alternatives
D. monitor the competition
E. specify objectives
116. Option A has a payoff of $10,000 in environment 1
and $20,000 in environment 2. Option B has a payoff of $5,000 in environment 1
and $27,500 in environment 2. Once the probability of environment 1 exceeds
______, option A becomes the better choice.
A. .40
B. .45
C. .50
D. .57
E. .60
A. .40
B. .45
C. .50
D. .57
E. .60
117. Option A has a payoff of $10,000 in environment 1
and $20,000 in environment 2. Option B has a payoff of $12,500 in environment 1
and $17,500 in environment 2. Once the probability of environment 2 exceeds
______, option A becomes the better choice.
A. .33
B. .67
C. .45
D. .50
E. .55
A. .33
B. .67
C. .45
D. .50
E. .55
118. Which of the following would make decision trees
an especially attractive decision making tool?
A. The need to think through a possible sequence of decisions
B. The need to maximize the expected value of perfect information
C. The need to minimize expected regret
D. The need to avoid suboptimization
E. The need to minimize costs
A. The need to think through a possible sequence of decisions
B. The need to maximize the expected value of perfect information
C. The need to minimize expected regret
D. The need to avoid suboptimization
E. The need to minimize costs
1.
Continuous processing is the best way to produce customized output.
2. As a
general rule, continuous processing systems produce products for inventory
rather than for customer order.
3. A
Job-Shop processing system generally requires less skilled workers than a
continuous processing system.
4.
Avoiding bottlenecks is the primary goal of product design.
5. In
general, Job-Shop systems have a lower unit cost than continuous systems do
because continuous systems use costly specialized equipment.
6. A
robot consists of three parts: a power supply, a controller, and a mechanical
arm.
7. Continuous
production has been a significant factor underpinning the U.S. standard of
living over the last century.
8.
Right-sized equipment tends to be larger than equipment used in traditional
process layout.
9.
Intermittent processing can take the form of batch processing or a job shop.
10. The
term computer aided manufacturing (CAM) refers primarily to the use of robotics
in a manufacturing process.
11.
Flexible manufacturing systems (FMS) bring the benefits of automation to
continuous processes.
12. Repetitive
processing systems usually produce goods specifically for customer orders
rather than for inventory.
13.
Morale problems can be a reason for redesign of a facility layout.
14. There
are three basic process types – Input,
Processing and Output.
15. A
cafeteria line would be an example of a process focused layout.
16. A
possible disadvantage of a product layout is an inflexible system.
17.
Product layouts involve high utilization of labor and equipment.
18. A
manufacturing cell allows the production of a wide-range of very different
products.
19.
Product layouts can more easily adapt to variations in product requirements
than process layouts can.
20.
Process layouts feature departments or other functional groupings of personnel
or equipment.
21. Information
technology refers to competitive data.
22. A
process layout is more susceptible to shutdowns caused by equipment breakdowns
than a product layout.
23.
Accounting, purchasing, and inventory control are fairly routine with process
layouts.
24. A disadvantage
of a product layout can be high in-process inventory costs.
25. In
cellular manufacturing, machines and equipment are grouped by type (e.g., all
grinders are grouped into a cell).
26. Among
the benefits claimed for cellular manufacturing are less material handling and
reduced setup time.
27. Group
technology is closely connected to cellular manufacturing.
28. The
percentage of idle time in an assembly line is called cycle time.
Chapter
06 - Process Selection and Facilities Layout
29.
Mismatches between operational capabilities and market demand can have a
negative impact on an organization.
30.
Service layouts must be visually pleasing as well as functional.
31.
"Balance delay" is another name for the percentage of idle time in a
product layout.
32.
"Balance delay" is another name for the percentage of idle time in a
process layout.
33. For a
production line, daily capacity can be determined by dividing the daily
operating time by the line's cycle time.
34. The
minimum number of workstations for a production line is determined by the
desired output rate.
35. The
goal of line balancing is to assign tasks to workstations in such a way that
the workstations have approximately equal time requirements.
36. An
idle percentage of zero means a line is perfectly balanced.
37. None
of the approaches to line balancing, manual or computerized, guarantee optimal
solutions.
38.
Heuristic approaches to line balancing are the only approach that will
guarantee an optimal solution.
39. The
main issue in the design of process layouts concerns the relative positioning
of the departments involved.
40. An
advantage of a U-shaped production line is that it facilitates teamwork and
flexibility in work assignments.
41. The
goal in line balancing is to obtain a reasonable allocation of work to each
station.
42. Cycle
time is the maximum time allowed for each workstation to complete its work on
each unit.
43. The
design of service layouts, e.g., warehouse and supermarket layouts, focuses on
cost minimization and product flow.
44.
Process layouts allow greater flexibility in processing than product layouts.
45.
Process layouts tend to have low in-process inventories.
46.
Flexibility can be used as a competitive strategy.
47. Poor
layouts are found in both manufacturing and service organizations.
48.
Numerically controlled (N/C) machine and some robots are applications of
programmable automation.
49. Which
of the following is not a process commonly considered in making products or
delivering services?
A.
continuous
B. batch
C.
repetitive
D. job
shop
E. subcontracting
50. The
type of processing system which is used for highly standardized products is:
A. continuous
B.
intermittent
C.
project
D. batch
E. unit
51.
Cellular layout is a term associated with:
A.
wireless telecommunication
B. part
families
C.
functional (or process) layouts
D.
assembly lines
E. job
shops
52. The
substitution of machinery that has sensing and control devices for human labor
is best described by the term:
A. automation
B.
feedback control
C.
computer-aided manufacturing
D.
computer-integrated manufacturing
E.
flexible manufacturing system
53.
Computer-aided manufacturing (CAM) refers to the use of computers in:
A.
product design
B.
decision making
C. data
analysis
D.
quality control
E. process
control
54. A
group of machines including supervisory computer control, automatic material
handling, and possibly robots is called:
A.
computer aided design
B. a
manufacturing cell
C.
computer-aided manufacturing
D.
computer-integrated manufacturing
E. a
flexible manufacturing system
55. In
which type of operations are you likely to see, at most, only minor variations
in the product or service being produced using the same process and the same
equipment?
A. a
project
B. a job
shop
C. repetitive
production
D. batch processing
E.
continuous production
56. The
process of assigning tasks to workstations in such a way that the workstations
have approximately equal time requirements is called:
A. fair
employment practices
B. idle
time analysis
C. line
balancing
D. cycle
time optimization
E. none
of the above
57. An
operations strategy for process selection should recognize that:
A.
process selection seldom requires technical expertise
B.
engineering "white elephants" are uncommon
C. there
is little need to manage technology
D. flexibility
is not always the best choice
E. most
technical skills can be contracted out to consultants
58.
Layout planning is required because of:
(I)
Efficient operations
(II)
Accidents or safety hazards
(III) New
products or services
(IV)
Morale problems
A. I and
II
B. II and
IV
C. I and
III
D. II, III,
and IV
E. I, II,
III, and IV
59. The
advantages of automation include:
(I)
Reduced output variability
(II)
Reduced variable costs
(III)
Machines don't strike or file grievances.
(IV)
Machines are always less expensive than human labor.
A. I and
IV
B. II and
III
C. I, II,
and III
D. I and
III
E. II and
IV
60. The
benefits of flexible manufacturing systems (FMS) include:
A.
reduced labor costs
B. higher
flexibility than automation
C. quick
changeover from part to part
D. significantly
lower unit costs
E. all of
the above
61. Which
type of processing system tends to produce the most product variety?
A.
Assembly
B. Job-Shop
C. Batch
D.
Continuous
E.
Project
62. In
which type of processing system would gasoline be produced from crude oil?
A. Job
Shop
B. Batch
C.
Assembly
D. Continuous
E.
Project
63. Which
of the following is not a characteristic of layout decisions in system design?
A.
substantial investment of both money and effort
B.
long-term commitment
C.
significant impact on short-term efficiency
D. usually
well-received by operative personnel
E. all of
the above
64. An
example of automated services is
A. on-line
banking
B. build
your own pizza
C.
haircuts
D.
massage parlors
E. all
are examples of automated services
65. Which
one of the following is not common to product layouts?
A. a high
rate of output
B.
specialization of labor
C. low
unit costs
D. ability
to adjust to changes in demand
E. all
are common
66. Which
one of the following is not considered an important factor in service layout
design?
A. cost
minimization and product flow
B.
frequency of orders
C.
customer attitude and image
D. all
are important
E. none
are important
67. The
type of layout which features departments or other functional groupings in
which similar activities are performed is:
A. process
B.
product
C.
fixed-position
D. mass
E. unit
68. Which
of the following is not true about process layouts when they are compared to
product layouts?
A. higher
in-process inventories
B. lower
span of supervision
C. lower
rates of output
D. more
involved cost accounting
E. lower
unit costs
69. The
type of layout in which workers, materials, and equipment are moved to the
product as needed is:
A.
process
B.
product
C. fixed-position
D. batch
E. mass
70. The
grouping of equipment by the operations needed to perform similar work for part
families is:
A.
product layout
B. cellular
manufacturing layout
C.
functional layout
D.
fixed-position layout
E.
process layout
71. Which
term is most closely associated with cellular manufacturing?
A. part
families
B.
assembly line
C.
robotics
D. CAD
E. CAM
72. Laser
technology used in surgical procedures is an example of technological advances
in:
A.
Product
B.
Service
C. Process
D.
Information
E. Reverse
Engineering
73.
Product profiling links key product or service requirements to:
A. Market
conditions
B. Order
sizes
C.
Pricing strategies
D.
Schedule changes
E. Process
capabilities
74.
Layout design has many objectives, one of which is _______.
A. reduce
bottlenecks
B. move
materials and workers simultaneously
C. use
workers and space efficiently
D. hold
material handling costs to 27% or less
E.
install computer terminals every 500 feet
75. Which
phrase most closely describes flexible manufacturing systems?
A. a
variation of CAD
B. a more
fully automated version of cellular manufacturing
C.
manufacturing resource planning
D. a
process layout with a manufacturing overlay
E. an
approach that allows workers to begin work at a time of their choosing
76. A
service organization (for example, a hospital) is likely to use a ________
layout because of variability in customer processing requirements.
A.
project
B. process
C. flow
D.
assembly
E.
non-repetitive
77. In a
product layout, the task of deciding how to assign work to specific stations is
referred to as:
A.
process balancing
B. task
allocation
C. line
balancing
D. work
allocation
E.
station balancing
78. The
minimum possible cycle time in a product layout is determined by the:
A. longest
task time
B. shortest
task time
C.
average task time
D. total
task time
E. none
of the above
79. A
production line is to be designed for a job with three tasks. The task times
are 0.4 minutes, 1.2 minutes, and 0.5 minutes. The maximum cycle time in
minutes is:
A. 0.3
B. 0.7
C. 1.4
D. 2.1
E. 0.8
80. A
production line is to be designed for a job with three tasks. The task times
are 0.3 minutes, 1.4 minutes, and 0.7 minutes. The minimum cycle time in
minutes, is:
A. 0.3
B. 0.7
C. 1.4
D. 2.4
E. 0.8
81. Daily
capacity of a product layout is determined by:
A. cycle
time divided by operating time
B. operating
time divided by cycle time
C.
operating time divided by total task time
D. total
task time divided by cycle time
E. cycle
time divided by total task time
82. The
maximum allowable cycle time is computed as:
A. daily
operating time divided by the desired output
B.
desired output divided by the daily operating time
C. daily
operating time divided by the product of the desired output and the sum of job
times
D. the
product of desired output and the sum of job times divided by daily operating
time
E. 1.00
minus station time
83. If a
line is balanced with 80 percent efficiency, the "balance delay"
would be:
A. 20
percent
B. 80
percent
C. 100
percent
D.
unknown, since balance delay isn't related to efficiency
E.
depends on the next operation
84. The
main issue in the design of process layouts for service operations concerns the
relative positioning of:
A.
workstations
B.
processing components
C. departments
D.
entrances, loading docks, etc.
E.
manufacturing cells
85. Which
of the following is not an information requirement for the design of a process
layout?
A. a list
of departments or work centers
B. a
projection of work flows between the work centers
C. the
distance between locations
D. the
cost per unit of distance to move loads
E. a list of
product cycle times for every product manufactured
86. Which
of the following is not an approach that companies use to achieve a smooth flow
of production?
A. line
balancing heuristics
B. parallel
workstations
C.
dynamic line balancing (Cross train workers)
D. mixed
model line
E. Companies
use all of these.
87. A
common goal in designing process layouts is:
A.
minimizing the number of workers
B.
minimizing idle time
C. minimizing
transportation costs
D.
maximizing work-station productive time
E.
maximizing transportation distances
88. In
the use of closeness ratings for process layouts, the code "U" means
the closeness between two departments is:
A.
(U)nknown
B.
(U)nusually important
C. of
(U)sual importance
D. (U)nimportant
E.
(U)ndesirable
89. Which
closeness rating reflects the undesirability of having two departments located
near each other?
A. A
B. E
C. I
D. U
E. X
90. Which
closeness rating reflects the highest importance for two departments being
close to each other?
A. A
B. E
C. I
D. U
E. X
91. Which
closeness rating reflects indifference on the nearness or lack of nearness of
two departments?
A. A
B. E
C. I
D. U
E. X
92.
Heuristic rules are used primarily in which of these types of layouts?
(I)
Product
(II)
Process
(III)
Fixed-position
A. I
B. II
C. I and
III
D. I and II
E. II and
III
93.
Heuristic rules are usually applied when:
A. an
optimum is necessary
B. a
computer program isn't available
C. a
problem has a small number of alternatives
D. a problem
has a large number of alternatives
E. other
approaches have failed
94. An
advantage of a U-shaped production line is that it:
A. is
more compact.
B.
permits better communication among employees.
C.
facilitates teamwork among workers.
D. increases
flexibility of work assignments.
E. all of
the above
95. Which
of these items would be most likely to be made with a fixed position layout?
A. a Boeing
777 jet aircraft
B.
applesauce
C. a
computer chip
D.
toothpaste
E. all of
these
96. A
product focused, single piece flow, pull production system would be called a:
A. cellular
layout
B. job
shop
C.
assembly line
D.
non-repetitive process
E.
continuous flow
97. Which
one of these is a tool used to tell a machine the details of the operations to
be performed?
A. CNC
B. CIM
C. CAD
D. CAM
E.
automation
98. Which
of the following is a primary concern for process selection?
A.
variety in products/services
B.
flexibility of equipment
C. volume
of output
D. all of
the above
E. none
of the above
99.
Management wants to design an assembly line that will turn out 800 videotapes
per day.There will be eight working hours in each day. The industrial
engineering staff has assembled the information below:
(A)
Determine the maximum and minimum cycle times.
(B) Determine
the optimum cycle time.
(C) What
is the minimum number of stations needed?
(D) Draw
the precedence diagram.
(E)
Assign tasks to stations in order of most following tasks first.
(A)
Maximum cycle time is 2.3 minutes; minimum cycle time is .6 minutes.
D) Refer
to the diagram above.
E) Refer
to the diagram above
100.
Given the information below, assign departments to locations in a 3 x 3 grid,
with department F in the lower right hand corner.
101.
Given the information below, assign the departments A through I to locations in
a 3 x 3 rid, with department E fixed in the lower right-hand corner.
102.
Determine the minimum number of workstations needed for this situation:
103.
Given the following data:
Determine
the percentage idle time.
(1.)
Compute the station idle time and the total idle time per cycle:
104.
Given the following process layout data for locating six departments in the six
areas shown: What process layout(s) satisfy(ies) these closeness ratings? Any
layout with I and VI at one end of the facility, III and IV at the other end,
and II and V in the middle.
A company
is designing a product layout for a new product. It plans to use this
production line eight hours a day in order to meet projected demand of 480
units per day. The tasks necessary to produce this product:
105.
Without regard to demand, what is the minimum possible cycle time (in seconds)
for this situation?
A. 162
B. 72
C. 54
D. 12
E. 60
106. If
the company desires that output rate equal demand, what is the desired cycle
time (in seconds)?
A. 162
B. 72
C. 54
D. 12
E. 60
107. If
the company desires that output rate equal demand, what is the minimum number
of workstations needed?
A. 3
B. 4
C. 5
D. 6
E. 7
108. If
the company desires that output rate equal demand, what would be the efficiency
of this line with the minimum number of workstations?
A. 100%
B. 92.5%
C. 75%
D. 87.5%
E. 90%
109. If
the company desires that output rate equal demand, what is the last task
performed at the second workstation in the balance which uses the minimum number
of workstations?
A. u
B. v
C. w
D. x
E. y
110.
Without considering forecasted demand, what is the minimum possible cycle time
for this production line?
A. 10
seconds
B. 20
seconds
C. 34
seconds
D. 38
seconds
E. 152
seconds
111. For
output to equal forecasted demand, what should be the actual cycle time for
this production?
A. 32
seconds
B. 38
seconds
C. 40
seconds
D. 76
seconds
E. 152
seconds
112. For
output to equal forecasted demand, what is the minimum number of workstations
needed?
A. 1
B. 3
C. 3.75
D. 4
E. 5
113. For
output to equal forecasted demand, what will be the efficiency of the
production line that uses the least number of workstations?
A. 81%
B. 90%
C. 95%
D. 85%
E. 100%
114. For
output to equal forecasted demand, what will be the second task performed at
the second workstation of the production line that uses the fewest number of
stations?
A. a
B. b
C. c
D. d
E. e
115.
Without considering projected demands, what is the minimum possible cycle time
for this production line?
A. 54
seconds
B. 14
seconds
C. 12
seconds
D. 10
seconds
E. 4
seconds
116. For
output to equal projected demand, what should be the actual cycle time for this
production line?
A. 54
seconds
B. 27
seconds
C. 20
seconds
D. 18
seconds
E. 14
seconds
117. For
output to equal projected demand, what is the minimum number of workstations
needed?
A. 6
B. 4.5
C. 3
D. 2.7
E. 2
118. For
output to equal projected demand, what will be the efficiency of the production
line that uses the minimum number of workstations?
A. 90%
B. 95%
C. 97%
D. 99%
E. 100%
119. For
output to equal projected demand, what will be the first task performed at the
third workstation of the production line which uses the minimum number of
stations?
A. u
B. v
C. w
D. x
E. y
120.
Without regard to projected demand, what is the minimum possible cycle time for
this assembly line?
A. 0
seconds
B. 3
seconds
C. 9 seconds
D. 10
seconds
E. 28
seconds
121. For
output to equal projected demand, what should be the actual cycle time for this
assembly line?
A. 0
seconds
B. 3 seconds
C. 9
seconds
D. 10
seconds
E. 28
seconds
122. For
output to equal projected demand, what is the minimum number of workstations
needed?
A. 2
B. 2.8
C. 3
D. 4
E. 5
123. For
output to equal projected demand, what will be the efficiency of the assembly
line that uses the minimum number of workstations?
A. 0.0%
B. 6.7%
C. 70.0%
D. 93.3%
E. 100%
124. For
output to equal projected demand, what will be the idle time at the second
workstation of the assembly line that uses the minimum number of workstations?
A. 0
seconds
B. 1 second
C. 2
seconds
D. 3
seconds
E. 5
seconds
125. What
is the distance (in meters) from area III to area I in this new facility?
A. 0
B. 10
C. 20
D. 30
E. 40
126. What
is the total flow (loads per week) between department Y and department Z?
A. 140
B. 160
C. 200
D. 250
E. 300
127. If
departments X, Y, and Z were to be located in areas I, II, and III,
respectively, what would be the total distance (in meters) loads would be moved
each week?
A. 4,000
B. 4,500
C. 7,000
D. 8,000
E. 9,000.
128. What
are total weekly costs for the least costly process layout?
A. $2,800
B. $3,150
C. $3,500
D. $4,000
E. $4,500
129. How
many least costly process layouts are there?
A. 1
B. 2
C. 3
D. 4
E. 5
130. What
is the distance (in meters) from area 3 to area 1 of this new facility?
A. 0
B. 10
C. 20
D. 30
E. 40
131. What
is the total flow (loads per week) between department Y and department Z?
A. 130
B. 150
C. 180
D. 230
E. 280
132. If
the company were to locate departments X, Y, and Z in areas 1, 2, and 3,
respectively, what would be the total distance (in meters) loads would be moved
each week?
A. 3,100
B. 3,600
C. 6,200
D. 7,200
E. 8,200
133. What
is the layout that will minimize the total distance loads will be moved each
week?
A. X in
1; Y in 2; Z in 3
B. X in 1; Z
in 2; Y in 3
C. Y in
1; X in 2; Z in 3
D. Z in
1; X in 2; Y in 3
E. Z in
1; Y in 2; X in 3
134. What
are total weekly costs for an optimum layout?
A. $3,100
B. $3,600
C. $6,200
D. $7,200
E. $8,200
135. What
is the distance (in meters) from area IV to area II in this new facility?
A. 0
B. 5
C. 10
D. 15
E. 20
136. What
is the total flow (patients per week) between department W and department L?
A. 70
B. 80
C. 88
D. 130
E. 148
137. How
many different process layouts are possible for this new facility?
A. 4
B. 6
C. 16
D. 24
E. 120
138. If
the consultant were to locate departments W, C, L, and E in areas I, II, III,
and IV, respectively, what would be total weekly costs?
A. $114
B. $217
C. $255
D. $322
E. $366
139. What
are total weekly costs for the least costly process layout?
A. $114
B. $217
C. $255
D. $322
E. $366
1. If the
elapsed time for the task is short and the activity is somewhat routine, a
modest amount of improvement occurs during the first few repetitions.
True False
True False
2. When the task is fairly complex and has a longer
duration, it will take a larger number of repetitions before improvement is
observed.
True False
True False
3. Negotiated purchasing results in lower unit costs
for smaller quantities.
True False
True False
4. Learning curves generally apply to situations in
which there is a high degree of human involvement and tasks are fairly
repetitive.
True False
True False
5. Learning curves are mostly relevant for complex,
new activities that have not been done often.
True False
True False
6. According to learning curve theory, every doubling
of total output will produce a constant percentage decrease in time per
unit.
True False
True False
7. The decrease in time between the second and fourth
units will be equal to the decrease in time between the first and second
units.
True False
True False
8. According to learning curve theory, for certain
kinds of tasks the cost per unit decreases as the number of repetitions
increases.
True False
True False
9. According to learning curve theory, the time
reduction per unit decreases (improves) as the number of units increase.
True False
True False
10. A learning percentage of 95% indicates greater
learning than a percentage of 90%.
True False
True False
11. A learning curve for an overqualified worker is
higher than an average worker.
True False
True False
12. An 80 percent learning curve means that with each
doubling of repetitions there will be a 20 percent decrease in time per
unit.
True False
True False
13. For an 80% learning curve, if the first unit
requires 10 hours, the second unit will require 8 hours and the third 6.4
hours.
True False
True False
14. If an 80% curve is appropriate for a task and the
first unit takes ten hours, the average time for the first two units would be
eight hours.
True False
True False
15. If we have never made the first unit but only
think we know how much the labor time will be, we cannot draw a learning
curve.
True False
True False
16. The learning curve principal would apply to the
number of students in a class - a class twice as large will learn 80%
faster.
True False
True False
17. The learning curve principle would apply to a
baseball pitcher learning to throw a curve ball.
True False
True False
18. The learning curve is a basic tool for mass
production type activities because it can deal with large volumes of
output.
True False
True False
19. Learning curves are used primarily for mass
production applications.
True False
True False
20. A learning rate of 98% implies an exceptionally
rapid rate of improvement.
True False
True False
21. A learning rate of 77% will produce relatively
minor decreases in completion times of the first few repetitions.
True False
True False
22. One use of learning curves is for negotiated
purchasing anticipating lower costs at the vendor with increasing
volumes.
True False
True False
23. A learning rate of 97% will produce minor
decreases in completion times of the first few repetitions.
True False
True False
24. The fact that human activities typically improve
when they are done on a repetitive basis is described by a/an:
A. normal distribution curve
B. learning curve
C. binomial distribution curve
D. exponential curve
E. fatigue factor allowance
A. normal distribution curve
B. learning curve
C. binomial distribution curve
D. exponential curve
E. fatigue factor allowance
25. To which worker would learning curves be most
applicable?
A. bus driver
B. printing press operator
C. assembly-line worker
D. auto service mechanic
E. baker or cook
A. bus driver
B. printing press operator
C. assembly-line worker
D. auto service mechanic
E. baker or cook
26. Once production is underway and the learning curve
effect is occurring, successive changes made to the production process will
cause the time per unit to:
A. continue following the original learning curve without any impact
B. cause a scallop effect
C. increase the unit time and result in a higher percentage learning curve
D. decrease the unit time and result in a higher percentage learning curve
E. decrease the unit time and result in a lower percentage learning curve
A. continue following the original learning curve without any impact
B. cause a scallop effect
C. increase the unit time and result in a higher percentage learning curve
D. decrease the unit time and result in a higher percentage learning curve
E. decrease the unit time and result in a lower percentage learning curve
27. On a log-log graph, learning curves appear
as:
A. upward-curving lines
B. downward-curving lines
C. straight lines
D. lines which increase at a decreasing rate
E. lines which decrease at a decreasing rate
A. upward-curving lines
B. downward-curving lines
C. straight lines
D. lines which increase at a decreasing rate
E. lines which decrease at a decreasing rate
28. Increasing volumes result in ___________ the
learning curve.
A. moving up
B. moving down
C. moving off
D. moving away from
E. stabilization of
A. moving up
B. moving down
C. moving off
D. moving away from
E. stabilization of
29. It took exactly 10 hours to perform the first
kidney transplant on a 100 percent learning curve. The second kidney transplant
will take how many hours to perform?
A. 8.0 hours
B. 10.0 hours
C. 12.0 hours
D. A 100 percent learning curve cannot exist.
E. 5 hours
A. 8.0 hours
B. 10.0 hours
C. 12.0 hours
D. A 100 percent learning curve cannot exist.
E. 5 hours
30. A job is expected to have a 70 percent learning
curve. The first unit has been completed in 20 hours. Accordingly, the second
unit can be expected to take approximately how many hours?
A. 6
B. 9.8
C. 14
D. 20
E. 34
A. 6
B. 9.8
C. 14
D. 20
E. 34
31. A job with a 70 percent learning curve required 20
hours for the initial unit. The fourth unit should require approximately how
many hours?
A. 6
B. 9.8
C. 14
D. 20
E. 34
A. 6
B. 9.8
C. 14
D. 20
E. 34
32. How long would a job with a 70 percent learning
curve and a time of 20 hours for the first unit require (approximately, in
hours) for the third unit?
A. 14.1
B. 11.5
C. 10.0
D. 7.8
E. 4.3
A. 14.1
B. 11.5
C. 10.0
D. 7.8
E. 4.3
33. A job is expected to have a learning curve of 90
percent. The third unit required 16 hours. The twelfth unit should take
approximately how many hours?
A. 2.67
B. 4.83
C. 7.94
D. 10.31
E. 12.95
A. 2.67
B. 4.83
C. 7.94
D. 10.31
E. 12.95
34. A job has an 80 percent learning curve. The second
unit required 12 hours to complete. Approximately how many hours will be
devoted to the first five units (including those already completed)?
A. 26
B. 36
C. 46
D. 56
E. 66
A. 26
B. 36
C. 46
D. 56
E. 66
35. A manager is trying to estimate the appropriate
learning curve for a certain job. The manager notes that the first four units
had a total time of 30 minutes. Which learning curve would yield approximately
this result if the first unit took 10 minutes?
A. .70
B. .75
C. .80
D. .85
E. .90
A. .70
B. .75
C. .80
D. .85
E. .90
36. In which of the following managerial activities
would learning curves probably be the least useful?
A. negotiated purchasing
B. manpower planning
C. location analysis
D. budgeting
E. pricing new products
A. negotiated purchasing
B. manpower planning
C. location analysis
D. budgeting
E. pricing new products
37. Which of the following is not a major caution or
criticism of learning curves?
A. Learning rates may differ between organizations.
B. Projections should be regarded as approximations.
C. The base time must be carefully determined.
D. The curve may eventually tip upwards.
E. Carryover effects may alter the learning rate.
A. Learning rates may differ between organizations.
B. Projections should be regarded as approximations.
C. The base time must be carefully determined.
D. The curve may eventually tip upwards.
E. Carryover effects may alter the learning rate.
38. A job has a 70% learning curve. If the first unit
took 10 hours to complete, the third unit should take roughly how many
hours?
A. 7
B. 5.5
C. 5
D. 3.5
E. 4.9
A. 7
B. 5.5
C. 5
D. 3.5
E. 4.9
39. A job has an 80% learning curve. If the first unit
took 40 hours to complete, the fourth unit should take roughly how many
hours?
A. 20
B. 25
C. 31
D. 35
E. 40
A. 20
B. 25
C. 31
D. 35
E. 40
40. Which one of the following would learning curves
probably affect the least?
A. pricing new products
B. negotiated purchasing
C. layout analysis
D. scheduling
E. capacity planning
A. pricing new products
B. negotiated purchasing
C. layout analysis
D. scheduling
E. capacity planning
41. A job has an 80% learning curve. If the first unit
took 50 hours to complete, the third unit should take roughly how many
hours?
A. 40
B. 36
C. 35
D. 32
E. 10
A. 40
B. 36
C. 35
D. 32
E. 10
42. Unit times for a job exhibit a learning effect. If
the 2nd unit took 30 hours, and the 4th unit took 21
hours, roughly how many hours would you estimate the 3rd unit
took?
A. 29
B. 27
C. 25
D. 24
E. 21
A. 29
B. 27
C. 25
D. 24
E. 21
43. A
manager is trying to estimate the learning rate for a new job. The first unit
took 16 hours and the fourth unit required about 13 hours. The learning rate
is:
A. 70%
B. 75%
C. 80%
D. 85%
E. 90%
A. 70%
B. 75%
C. 80%
D. 85%
E. 90%
44. A job will have a learning rate of 75 percent. If
the 3rd unit requires 10 hours, the 12th unit should
require about this many hours:
A. 5.6
B. 6.5
C. 7.4
D. 8.3
E. 9.2
A. 5.6
B. 6.5
C. 7.4
D. 8.3
E. 9.2
45. Assembly
of a model airplane has a learning curve of 80 percent. The estimated time to
assemble a second identical model airplane is 40 hours. Determine approximately
how much time will be required for:
(A) the eighth unit
(B) the first ten units
(A) the eighth unit
(B) the first ten units
46. Developing
work assignments in a job shop in a certain firm has a learning curve of 80
percent. If the second set of assignments takes 12 minutes, determine the
length of time required for the following:
(A) the fifth set
(B) sets 3, 4, and 5 together
(A) the fifth set
(B) sets 3, 4, and 5 together
47. An
order we just received has a 90 percent learning curve associated with it. The
second unit of the total 25-unit order had a unit time of 36 minutes. What will
the total time be for the entire order (all 25 units)?
48. Sally
suspects strongly that there is a learning curve associated with solving
problems assigned for operations management. She notes that it took her
approximately 33 minutes to solve the first problem and 17 minutes to solve the
fifth problem.
(A) Estimate Sally's learning percentage.
(B) Using your answer from Part A, estimate how long it will take Sally to finish the three remaining problems.
(A) Estimate Sally's learning percentage.
(B) Using your answer from Part A, estimate how long it will take Sally to finish the three remaining problems.
49. Ron
has noted that the first accounting problem he did in a set of similar problems
took him one hour, and the ninth problem took 24 minutes.
(A) Estimate Ron's learning curve.
(B) About how long did it take Ron to do his set of 10 problems?
(A) Estimate Ron's learning curve.
(B) About how long did it take Ron to do his set of 10 problems?
50. It
takes a worker with a 90 percent learning curve 72.9 minutes to complete the
fourth unit of a seven-unit job. Estimate the amount of time the worker spent
on the first two units.
51. The 3rd
unit of a ten-unit job required 7.3 hours to complete. The 4th unit
has been worked on for two hours, but it is not yet finished. Estimate the
remaining amount of time that will be needed to finish this ten-unit job if the
work has an 80% learning curve.
A
company is preparing a bid on a government contract for 40 units of a certain
product. The operations manager estimates the assembly time required for the
first two units to be 10.4 hours and 8.8 hours respectively.
52. What is the appropriate learning curve?
A. 70 percent
B. 75 percent
C. 80 percent
D. 85 percent
E. 90 percent
A. 70 percent
B. 75 percent
C. 80 percent
D. 85 percent
E. 90 percent
53. What is the expected time required to
produce the 40th unit?
A. 3.2 hours
B. 4.4 hours
C. 5.9 hours
D. 3.7 hours
E. 2.2 hours
A. 3.2 hours
B. 4.4 hours
C. 5.9 hours
D. 3.7 hours
E. 2.2 hours
54. What is the average time per unit for the first 30
units?
A. 4.7 hours
B. 5.9 hours
C. 5.6 hours
D. 4.5 hours
E. 3.6 hours
A. 4.7 hours
B. 5.9 hours
C. 5.6 hours
D. 4.5 hours
E. 3.6 hours
55. If a contract for 30 units is canceled after the
first 20 units, approximately how much of the expected total direct labor will
have been expended to that point?
A. 73%
B. 55%
C. 61%
D. 50%
E. It is impossible to say without additional information.
A. 73%
B. 55%
C. 61%
D. 50%
E. It is impossible to say without additional information.
56. Approximately how long will it take to produce the
15th unit?
A. 4.3 hours
B. 5.5 hours
C. 4.7 hours
D. 6.9 hours
E. 3.4 hours
A. 4.3 hours
B. 5.5 hours
C. 4.7 hours
D. 6.9 hours
E. 3.4 hours
57. Which unit, if any, will require approximately
one-half the time of the first unit?
A. 18th unit
B. 19th unit
C. 20th unit
D. 21st unit
E. 22nd unit
A. 18th unit
B. 19th unit
C. 20th unit
D. 21st unit
E. 22nd unit
58. Approximately how long will it take to produce the
25th through the 30th units?
A. 23 hours
B. 49 hours
C. 29 hours
D. 38 hours
E. It is impossible to say without additional information.
A. 23 hours
B. 49 hours
C. 29 hours
D. 38 hours
E. It is impossible to say without additional information.
A manager wants to analyze the learning curve
associated with producing one of his company's products. Accordingly, he has
gathered the following data:
59. What is the learning curve percentage?
A. 40%.
B. 50%.
C. 75%.
D. 80%.
E. 90%.
A. 40%.
B. 50%.
C. 75%.
D. 80%.
E. 90%.
60. How long did it take to produce the first
unit?
A. 5 hours
B. 6 hours
C. 6.25 hours
D. 6.33 hours
E. 6.5 hours
A. 5 hours
B. 6 hours
C. 6.25 hours
D. 6.33 hours
E. 6.5 hours
61. Approximately how long did it take to produce the
first four units?
A. 15 hours
B. 16 hours
C. 18 hours
D. 20 hours
E. 21 hours
A. 15 hours
B. 16 hours
C. 18 hours
D. 20 hours
E. 21 hours
62. Approximately how long will it take to produce the
tenth unit?
A. 1 hour
B. 2 hours
C. 3 hours
D. 4 hours
E. 5 hours
A. 1 hour
B. 2 hours
C. 3 hours
D. 4 hours
E. 5 hours
63. Approximately how long will it take to produce the
fifth through tenth units?
A. 15 hours
B. 16 hours
C. 18 hours
D. 20 hours
E. 21 hours
A. 15 hours
B. 16 hours
C. 18 hours
D. 20 hours
E. 21 hours
64. In which of the following scenarios would an 80%
learning curve be especially relevant?
A. the pursuit of an innovation strategy to stay ahead of competitors
B. the pursuit of a flexibility-based strategy to increase customer satisfaction
C. the pursuit of a customization-based strategy to command premium prices
D. the pursuit of a time-based strategy to gain market share
E. the pursuit of a quality-based strategy to gain customer loyalty
A. the pursuit of an innovation strategy to stay ahead of competitors
B. the pursuit of a flexibility-based strategy to increase customer satisfaction
C. the pursuit of a customization-based strategy to command premium prices
D. the pursuit of a time-based strategy to gain market share
E. the pursuit of a quality-based strategy to gain customer loyalty
65. To which of the following challenges are learning
curves important considerations?
A. capacity planning
B. product designs
C. process layouts
D. output-based compensation
E. demand forecasting
A. capacity planning
B. product designs
C. process layouts
D. output-based compensation
E. demand forecasting
66. Which of the following is an example of a
carryover effect?
A. capacity that was used on older products but that can be used on new products
B. previous experience that is relevant to the current scenario
C. existing products that are still in the maturity phase of their life cycle
D. forecasting errors from previous product lines
E. old supplier contracts that must still be honored
A. capacity that was used on older products but that can be used on new products
B. previous experience that is relevant to the current scenario
C. existing products that are still in the maturity phase of their life cycle
D. forecasting errors from previous product lines
E. old supplier contracts that must still be honored
67. When are learning curves most relevant to
managerial decision making in mass production settings?
A. late in product life-cycles
B. in the maturity phase
C. in the decline phase
D. before processes are stabilized
E. never
A. late in product life-cycles
B. in the maturity phase
C. in the decline phase
D. before processes are stabilized
E. never
68. Suppose the first unit required 800 hours and the
second unit required only 680. Which of the following times for the fourth unit
would be consistent with a true learning curve scenario?
A. 492
B. 587
C. 578
D. 603
E. 583
A. 492
B. 587
C. 578
D. 603
E. 583
1. Ergonomics is the use of
computers and robots in the workplace.
True False
True False
2. Specialization is one of the sources of
disagreement between the efficiency and behavioral approaches to job
design.
True False
True False
3. One disadvantage of specialization is worker
dissatisfaction.
True False
True False
4. The quickest, most effective way to improve an
employee's job satisfaction is increase his or her compensation.
True False
True False
5. Job enrichment involves giving a workers a greater
share of the total task which is why they feel enriched.
True False
True False
6. Trust is a factor influencing productivity.
True False
True False
7. Many lower level jobs are monotonous and
boring.
True False
True False
8. Job enrichment involves an increase in
the level of responsibility for planning and coordinating tasks.
True False
True False
9. "Self-directed teams" are allowed to make
changes in the work processes under their control.
True False
True False
10. "Self-directed teams" help other work
groups make changes to their processes.
True False
True False
11. Motivation influences quality and productivity,
but not the work environment.
True False
True False
12. One important factor that influences productivity
is trust between workers and managers.
True False
True False
13. Ergonomics is an important part of job design to
consider when we automate the system.
True False
True False
14. One of the potential benefits of
"self-directed teams" is higher productivity and greater worker
satisfaction.
True False
True False
15. One of the potential benefits of
"self-directed teams" is higher quality.
True False
True False
16. One potential disadvantage of "self-directed
teams" is higher training costs.
True False
True False
17. Job design relates to people therefore technology
has little impact.
True False
True False
18. Methods analysis cannot be done for new jobs (ones
that do not yet exist) since it requires observation of the process.
True False
True False
19. One therblig is the equivalent of one hour of
sustained work by one average person.
True False
True False
20. A flow process chart is helpful for visualizing
the portions of a work cycle during which the operator and equipment are busy
or idle.
True False
True False
21. Predetermined time standards are usually based on
observing one very efficient worker performing the task.
True False
True False
22. Therbligs are basic elemental motions.
True False
True False
23. We incorporate the average seriousness of
accidents by measuring the number of lost-time accidents per million
labor-hours worked.
True False
True False
24. Work measurement concentrates on how long the
tasks take to accomplish.
True False
True False
25. Ergonomics is important for preventing common
workplace injuries such as back injuries and repetitive-motion injuries.
True False
True False
26. The most widely used method of work measurement is
work sampling.
True False
True False
27. For purposes of obtaining good time standards
using a stopwatch time study, the analyst should try to avoid having the worker
discover he or she is being observed.
True False
True False
28. One factor in determining how many cycles to time
in a time study is the degree of variation that is present in the observed
times.
True False
True False
29. The normal time in time study is obtained by
multiplying the observed time by the performance rating.
True False
True False
30. Studies on worker efficiency and time of day
suggest the greatest efficiency is at the end of the day when workers are
‘warmed up'.
True False
True False
31. The normal time for a job is multiplied by the
performance rating to obtain the standard time for the job.
True False
True False
32. The design of work systems, because objective
standards are used, avoids most ethical issues.
True False
True False
33. The standard time for a job can be obtained by
multiplying the normal time by an appropriate allowance factor.
True False
True False
34. Predetermined time standards use historical data
from a company's own files.
True False
True False
35. A performance rating of less than 1.0 means that
the observed worker was judged to be working at a faster than normal rate -
doing the job quicker than normal.
True False
True False
36. Predetermined time standards involve the use of
published data regarding how long various activities are expected to
take.
True False
True False
37. Work sampling can be used to estimate the
proportion of time a machine is idle.
True False
True False
38. Work sampling involves the use of some method of
randomizing the observations.
True False
True False
39. An advantage of work sampling, compared to a
stopwatch time study, is that observations are spread out over a period of time
in work sampling.
True False
True False
40. No stopwatch is required in a work sampling
study.
True False
True False
41. Work sampling provides a detailed elemental
breakdown of a task for purposes of establishing reliable time standards.
True False
True False
42. Measured day work refers to an output-based
system.
True False
True False
43. It would be acceptable to use a group incentive
plan for an assembly line operation.
True False
True False
44. Work sampling provides both quick and accurate
estimates of activity times.
True False
True False
45. Methods analysis and motion study techniques do
not directly consider behavioral aspects of jobs.
True False
True False
46. "Time-based systems" compensate
employees according to the time the employee has worked and the amount of
output they produce.
True False
True False
47. "Output-based systems" compensate
employees according to the amount of output they produce, thereby tying pay
directly to performance.
True False
True False
48. A pay system that rewards workers who undergo
training that increases their skills is called a "knowledge-based pay
system."
True False
True False
49. "Knowledge-based pay systems" pay higher
wages or salaries to workers who have completed college than to those who just
finished high school.
True False
True False
50. Increasing compensation is always a way to improve
worker satisfaction.
True False
True False
51. A worker-machine chart can help identify non-productive
parts of a process.
True False
True False
52. A worker-machine chart can be used to determine
how many machines an operator can manage.
True False
True False
53. Micromotion studies should be limited to periodic
activities where breakthrough improvements are possible.
True False
True False
54. The Occupational Safety and Health Act (OSHA) is a
regulatory burden that has been proven to have little impact on the safety and
welfare of workers.
True False
True False
55. Management compensation should be based primarily
on organizational output.
True False
True False
56. Many management compensation systems are being
revised to reflect increased emphasis on quality and customer service.
True False
True False
57. Behavioral approaches to job design include:
A. Specialization
B. Ergonomics
C. Job Rotation
D. Flow Process Charts
E. SIMO Charts
A. Specialization
B. Ergonomics
C. Job Rotation
D. Flow Process Charts
E. SIMO Charts
58. A major advantage of job specialization in
business is increased _________.
A. motivation
B. opportunity for advancement
C. opportunity for self-fulfillment
D. productivity
E. job enrichment
A. motivation
B. opportunity for advancement
C. opportunity for self-fulfillment
D. productivity
E. job enrichment
59. Which of the following is not generally considered
an advantage of specialization?
A. high productivity
B. low wage costs
C. ease of training employees
D. low equipment costs
E. all are advantages
A. high productivity
B. low wage costs
C. ease of training employees
D. low equipment costs
E. all are advantages
60. Process chart symbols don't include
________.
A. Delay
B. Inspection
C. Operation
D. Rejection
E. Storage
A. Delay
B. Inspection
C. Operation
D. Rejection
E. Storage
61. Which of the following most closely describes job
enlargement?
A. horizontal loading
B. increasing the level of responsibility associated with a job
C. transferring workers through a series of jobs to increase their scope of experience
D. increasing the amount of workspace assigned to a worker
E. assigning two jobs to the same worker
A. horizontal loading
B. increasing the level of responsibility associated with a job
C. transferring workers through a series of jobs to increase their scope of experience
D. increasing the amount of workspace assigned to a worker
E. assigning two jobs to the same worker
62. A behavioral approach to job design which
increases responsibility for planning and coordinating tasks is job:
A. enlargement
B. rotation
C. enrichment
D. involvement
E. enhancement
A. enlargement
B. rotation
C. enrichment
D. involvement
E. enhancement
63. Which of the following concerns is not one that
job designers focus on?
A. what will be done in a job
B. who will do the job
C. how the job will be done
D. when should the job be completed
E. where the job will be done
A. what will be done in a job
B. who will do the job
C. how the job will be done
D. when should the job be completed
E. where the job will be done
64. Which of the following is not a potential benefit
of the use of self-directed teams?
A. higher quality
B. higher productivity
C. greater worker satisfaction
D. greater satisfaction for middle managers
E. lower turnover
A. higher quality
B. higher productivity
C. greater worker satisfaction
D. greater satisfaction for middle managers
E. lower turnover
65. A SIMO chart includes:
A. Delay
B. Storage
C. Transportation
D. Left/Right hand movements
E. Inspection
A. Delay
B. Storage
C. Transportation
D. Left/Right hand movements
E. Inspection
66. Determining the number of cycles to observe is an
element of ________.
A. Stop watch time study
B. Standard elemental times
C. Predetermined time standards
D. Work sampling
E. MTM tables
A. Stop watch time study
B. Standard elemental times
C. Predetermined time standards
D. Work sampling
E. MTM tables
67. The chart used to review the overall sequence of
an operation by focusing on either the movements of the operator or materials
is called a _________.
A. SIMO-chart
B. Gantt chart
C. Worker-materials chart
D. Flow process chart
E. Multi-activity chart
A. SIMO-chart
B. Gantt chart
C. Worker-materials chart
D. Flow process chart
E. Multi-activity chart
68. The methods analysis chart which describes the
overall sequence of operations, transportation, storage, delays, and inspection
is a:
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
69. The symbols for operation, storage,
transportation, inspection, and delay would usually be found on which type of
chart?
A. Flow process
B. Gantt
C. Simultaneous motion
D. Worker-machine
E. Delay analysis
A. Flow process
B. Gantt
C. Simultaneous motion
D. Worker-machine
E. Delay analysis
70. The chart used to focus on busy and idle portions
of a work cycle is a:
A. Worker-machine chart
B. Gantt chart
C. SIMO-chart
D. Idle chart
E. Flow process chart
A. Worker-machine chart
B. Gantt chart
C. SIMO-chart
D. Idle chart
E. Flow process chart
71. The methods analysis chart which describes the
portions of a work cycle during which an operator and equipment are busy or
idle is a:
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
72. In methods analysis, a "therblig" is
a:
A. charting method of analysis
B. job enrichment technique
C. dummy task
D. basic elemental motion
E. fraction (.0006) of a minute
A. charting method of analysis
B. job enrichment technique
C. dummy task
D. basic elemental motion
E. fraction (.0006) of a minute
73. The methods analysis chart which describes the
movements of both hands at the same time is a:
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
A. flow process chart
B. worker-machine chart
C. gang process chart
D. simultaneous-motion (SIMO) chart
E. time/efficiency chart
74. One form of long term team that is increasingly
being used, especially in lean production settings, is:
A. Quality circle
B. Product Design
C. Self-directed
D. Self-improvement
E. Mandatory
A. Quality circle
B. Product Design
C. Self-directed
D. Self-improvement
E. Mandatory
75. In a stopwatch time study, the number of cycles
that must be timed is a function of:
A. the variability of observed times
B. the desired accuracy for the estimated job time
C. the desired confidence for the estimated job time
D. all of the above
E. none of the above
A. the variability of observed times
B. the desired accuracy for the estimated job time
C. the desired confidence for the estimated job time
D. all of the above
E. none of the above
76. What is the effect of an increase in the desired
confidence level on the number of observations necessary in a time study?
A. increases
B. decreases
C. unaffected
D. may increase or decrease, depending on the sample standard deviation
E. impossible to say without additional information
A. increases
B. decreases
C. unaffected
D. may increase or decrease, depending on the sample standard deviation
E. impossible to say without additional information
77. In a stopwatch time study, the average time it
takes a given worker to perform a task a certain number of times is the:
A. observed time
B. normal time
C. standard time
D. allowance time
E. performance rating time
A. observed time
B. normal time
C. standard time
D. allowance time
E. performance rating time
78. Which is not a requirement for an effective
team?
A. talent and skills to meet goals.
B. one or more members representing supervision.
C. a system of reinforcement and celebration.
D. clearly stated and commonly held vision and goals.
E. effective and skilled interpersonal relations.
A. talent and skills to meet goals.
B. one or more members representing supervision.
C. a system of reinforcement and celebration.
D. clearly stated and commonly held vision and goals.
E. effective and skilled interpersonal relations.
79. A job had an observed cycle time of four minutes,
a performance rating of 80 percent, and an allowance factor that was 20 percent
of job time. Normal time for the job in minutes is:
A. 3.20
B. 3.84
C. 4.00
D. 4.80
E. 5.00
A. 3.20
B. 3.84
C. 4.00
D. 4.80
E. 5.00
80. When performing a time study, the analyst converts
the observed time into the time an "average" worker would require
working at an acceptable pace by using which of the following?
A. allowance factors
B. MTM
C. methods analysis
D. performance rating
E. analysis of therbligs
A. allowance factors
B. MTM
C. methods analysis
D. performance rating
E. analysis of therbligs
81. In stopwatch time study, adjusting the normal time
by an allowance factor for normal delays and interruptions results in
the:
A. observed time
B. normal time
C. standard time
D. allowance time
E. performance rating time
A. observed time
B. normal time
C. standard time
D. allowance time
E. performance rating time
82. A job had an observed time of 10 minutes, a
performance rating of .90, and an allowance factor of 20 percent of job time.
Twenty-five cycles were timed. Standard time for the job in minutes is:
A. 10.0
B. 10.8
C. 12.5
D. 15.0
E. depends on the number of cycles observed
A. 10.0
B. 10.8
C. 12.5
D. 15.0
E. depends on the number of cycles observed
83. A job has a normal time of 12 minutes, a
performance rating of .80, and an allowance factor of 20 percent of job time.
The standard time for this job in minutes is:
A. 11.52
B. 12
C. 14.4
D. 15
E. depends on the number of cycles observed
A. 11.52
B. 12
C. 14.4
D. 15
E. depends on the number of cycles observed
84. Standard times derived from a firm's historical
data are known as:
A. predetermined times
B. MTM
C. work sampling times
D. judgmental times
E. standard elemental times
A. predetermined times
B. MTM
C. work sampling times
D. judgmental times
E. standard elemental times
85. Allowance percentages normally would not
include:
A. noise levels
B. monotony
C. personal phone calls
D. weight lifted
E. rest room allowances
A. noise levels
B. monotony
C. personal phone calls
D. weight lifted
E. rest room allowances
86. A technique for estimating the proportion of time
a worker spends on various activities is:
A. stopwatch time study
B. standard elemental (historical) times
C. simultaneous motion study
D. predetermined (published) time standards
E. work sampling
A. stopwatch time study
B. standard elemental (historical) times
C. simultaneous motion study
D. predetermined (published) time standards
E. work sampling
87. The technique which can be used to estimate the
percentage of time a worker or piece of equipment is idle is known as:
A. MTM
B. work sampling
C. methods analysis
D. micro motion study
E. none of these
A. MTM
B. work sampling
C. methods analysis
D. micro motion study
E. none of these
88. Which sample proportion will require the largest
number of work sampling observations?
A. .05
B. .25
C. .50
D. .75
E. .95
A. .05
B. .25
C. .50
D. .75
E. .95
89. What will be the effect on sample size in work
sampling of increasing the permissible maximum error?
A. increase the number of observations needed
B. decrease the number of observations needed
C. no effect on sample size
D. sometimes increase and sometimes decrease the sample size, depending on the analyst
E. impossible to say without additional information
A. increase the number of observations needed
B. decrease the number of observations needed
C. no effect on sample size
D. sometimes increase and sometimes decrease the sample size, depending on the analyst
E. impossible to say without additional information
90. In work sampling, observations should be
taken:
A. at the same time each day
B. within a short period of time
C. at randomly determined times
D. once every hour
E. once every day
A. at the same time each day
B. within a short period of time
C. at randomly determined times
D. once every hour
E. once every day
91. Which of the following is not an advantage of work
sampling compared to stopwatch time study?
A. There is little or no disruption of work.
B. It is less susceptible to short-term fluctuations.
C. Workers are less resentful.
D. It is less costly and less time-consuming.
E. It is better suited for short, repetitive tasks.
A. There is little or no disruption of work.
B. It is less susceptible to short-term fluctuations.
C. Workers are less resentful.
D. It is less costly and less time-consuming.
E. It is better suited for short, repetitive tasks.
92. Which of the following is not characteristic of
time-based compensation plans?
A. stable labor costs
B. easier to administer than output-based plans
C. stable pay for workers
D. simpler wage computations than output-based plans
E. lower cost per unit than output-based plans
A. stable labor costs
B. easier to administer than output-based plans
C. stable pay for workers
D. simpler wage computations than output-based plans
E. lower cost per unit than output-based plans
93. Which of the following statements should not
characterize an operations strategy toward the design of work systems?
A. Manufacturing technology is the heart of a business.
B. Workers can make or break a business.
C. Workers can be a valuable source of insights.
D. A spirit of cooperation can contribute to success.
E. Workers can be proud and respected.
A. Manufacturing technology is the heart of a business.
B. Workers can make or break a business.
C. Workers can be a valuable source of insights.
D. A spirit of cooperation can contribute to success.
E. Workers can be proud and respected.
94. The design of work systems involves:
A. work measurement
B. job design
C. compensation
D. all of the above
E. use of outside human resource consultants
A. work measurement
B. job design
C. compensation
D. all of the above
E. use of outside human resource consultants
95. Methods analysis and motion study techniques
develop which aspect of jobs?
A. behavioral aspects
B. efficiency aspects
C. pay levels
D. all of the above
E. none of the above
A. behavioral aspects
B. efficiency aspects
C. pay levels
D. all of the above
E. none of the above
96. A disadvantage of teams is:
A. higher quality
B. higher productivity
C. greater worker satisfaction
D. team member conflict
E. lower turnover
A. higher quality
B. higher productivity
C. greater worker satisfaction
D. team member conflict
E. lower turnover
A Methods and Measurements
Analyst needs to develop a time standard for a certain task. In a preliminary
study, he observed one of his workers perform this task five times, with the
following results:
104. What is the observed time (OT) for this
task?
A. 80 seconds
B. 84 seconds
C. 160 seconds
D. 240 seconds
E. 400 seconds
A. 80 seconds
B. 84 seconds
C. 160 seconds
D. 240 seconds
E. 400 seconds
105. What is the normal time (NT) for this task if the
employee worked at a twenty-five percent faster pace than average?
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
106. What is the standard time (ST) for this task if
the employee worked at a twenty-five percent faster pace than is average and an
allowance of twenty percent of the workday is used?
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
107. What is the standard time (ST) for this task if
the employee worked at a twenty-five percent faster pace than is average and an
allowance of twenty percent of job time is used?
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
A. 80 seconds
B. 96 seconds
C. 100 seconds
D. 120 seconds
E. 125 seconds
108. How many observations should be made if the analyst
wants to be 99.74 percent confident that the maximum error in the observed time
is two seconds? Assume that the standard deviation of each task time is 4
seconds.
A. 5
B. 6
C. 25
D. 36
E. 49
A. 5
B. 6
C. 25
D. 36
E. 49
The owner of Kat Motel wants to develop a time
standard for the task of cleaning a cat cage. In a preliminary study, she
observed one of her workers perform this task six times, with the following
results:
109. What is the observed time (OT) for this
task?
A. 81 seconds
B. 90 seconds
C. 99 seconds
D. 108 seconds
E. 540 seconds
A. 81 seconds
B. 90 seconds
C. 99 seconds
D. 108 seconds
E. 540 seconds
110. What is the normal time (NT) for this task if the
employee worked at a fifty-percent faster pace than is average?
A. 45 seconds
B. 60 seconds
C. 90 seconds
D. 135 seconds
E. 180 seconds
A. 45 seconds
B. 60 seconds
C. 90 seconds
D. 135 seconds
E. 180 seconds
111. What is the standard time (ST) for this task if
the employee worked at a fifty-percent faster pace than is average, and an
allowance of twenty percent of job time is used?
A. 90 seconds
B. 99 seconds
C. 100 seconds
D. 162 seconds
E. 150 seconds
A. 90 seconds
B. 99 seconds
C. 100 seconds
D. 162 seconds
E. 150 seconds
112. What is the standard time (ST) for this task if
the employee worked at a fifty-percent faster pace than is average, and an
allowance of ten percent of the workday is used?
A. 90 seconds
B. 99 seconds
C. 100 seconds
D. 168.8 seconds
E. 150 seconds
A. 90 seconds
B. 99 seconds
C. 100 seconds
D. 168.8 seconds
E. 150 seconds
113. How many observations should be made if she wants
to be 95.44 percent confident that the maximum error in the observed time is
two seconds? Assume that the standard deviation of the task time is 6
seconds.
A. 5
B. 6
C. 30
D. 36
E. 49
A. 5
B. 6
C. 30
D. 36
E. 49
A Methods and Measurements Analyst for Timepiece,
Inc. needs to develop a time standard for the task of attaching a watch to a
wristband. In a preliminary study, he observed one of his workers perform this
task five times, with the following results:
114. What is the observed time (OT) for this
task?
A. 20 seconds
B. 27 seconds
C. 46 seconds
D. 66 seconds
E. 100 seconds
A. 20 seconds
B. 27 seconds
C. 46 seconds
D. 66 seconds
E. 100 seconds
115. What is the normal time (NT) for this task if the
employee worked at a twenty- percent faster pace than is average?
A. 16.7 seconds
B. 20 seconds
C. 24 seconds
D. 25 seconds
E. 100 seconds
A. 16.7 seconds
B. 20 seconds
C. 24 seconds
D. 25 seconds
E. 100 seconds
116. What is the standard time (ST) for this task if
the employee worked at a twenty- percent faster pace than is average, and an
allowance of twenty percent of the workday is used?
A. 20 seconds
B. 24 seconds
C. 25 seconds
D. 28.8 seconds
E. 30 seconds
A. 20 seconds
B. 24 seconds
C. 25 seconds
D. 28.8 seconds
E. 30 seconds
117. What is the standard time (ST) for this task if
the employee worked at a twenty-percent faster pace than is average, and an
allowance of twenty percent of job time is used?
A. 4.5 seconds
B. 5 seconds
C. 20 seconds
D. 28.8 seconds
E. 100 seconds
A. 4.5 seconds
B. 5 seconds
C. 20 seconds
D. 28.8 seconds
E. 100 seconds
118. How many observations should be made if he wants
to be 95.44 percent confident that the maximum error in the observed time is
one second? Assume that the standard deviation of the task time is 5
seconds.
A. 5
B. 10
C. 25
D. 100
E. 121
A. 5
B. 10
C. 25
D. 100
E. 121
A Methods and Measurement Analyst wants to develop a
time standard for a certain task. In a preliminary study, he observed one
worker perform the task six times with an average observed time of 20 seconds
and a standard deviation of 2 seconds.
119. What is the normal time (NT) for this task if the
employee worked at a twenty percent faster pace than is average?
A. 4 seconds
B. 16.7 seconds
C. 20 seconds
D. 24 seconds
E. 100 seconds
A. 4 seconds
B. 16.7 seconds
C. 20 seconds
D. 24 seconds
E. 100 seconds
120. What is the standard time (ST) for this task if
the employee worked at a twenty percent faster pace than is average, and an
allowance of twenty-five percent of the workday is used?
A. 20 seconds
B. 25 seconds
C. 26.7 seconds
D. 30 seconds
E. 32 seconds
A. 20 seconds
B. 25 seconds
C. 26.7 seconds
D. 30 seconds
E. 32 seconds
121. What is the standard time (ST) for this task if
the employee worked at a twenty percent faster pace than is average, and an
allowance of twenty-five percent of job time is used?
A. 20 seconds
B. 25 seconds
C. 26.7 seconds
D. 30 seconds
E. 32 seconds
A. 20 seconds
B. 25 seconds
C. 26.7 seconds
D. 30 seconds
E. 32 seconds
122. How many observations should be made if he wants
to be 95.44 percent confident that the maximum error in the observed time is
one second?
A. 3
B. 4
C. 13.3
D. 16
E. 25
A. 3
B. 4
C. 13.3
D. 16
E. 25
The owner of Touchdown Sports Bar wants to develop a
time standard for the task of mixing a specialty cocktail. In a preliminary
study, he observed one of his bartenders perform this task seven times with an
average of 90 seconds and a standard deviation of 5 seconds.
123. What is the normal time (NT) for this task if the
bartender worked at a twenty percent faster pace than is average?
A. 75 seconds
B. 90 seconds
C. 108 seconds
D. 110 seconds
E. 112.5 seconds
A. 75 seconds
B. 90 seconds
C. 108 seconds
D. 110 seconds
E. 112.5 seconds
124. What is the standard time (ST) for this task if
the bartender worked at a twenty percent faster pace than is average, and an
allowance of twenty percent of the workday is used?
A. 112.5 seconds
B. 120 seconds
C. 135 seconds
D. 144 seconds
E. 150 seconds
A. 112.5 seconds
B. 120 seconds
C. 135 seconds
D. 144 seconds
E. 150 seconds
125. What is the standard time (ST) for this task if
the bartender worked at a twenty percent faster pace than is average, and an
allowance of ten percent of job time is used?
A. 135 seconds
B. 123.8 seconds
C. 118.8 seconds
D. 120 seconds
E. 112.5 seconds
A. 135 seconds
B. 123.8 seconds
C. 118.8 seconds
D. 120 seconds
E. 112.5 seconds
126. How many observations should be made if he wants
to be 95.44 percent confident that the maximum error in the observed time is
one second?
A. 64
B. 86
C. 100
D. 144
E. 169
A. 64
B. 86
C. 100
D. 144
E. 169
A Methods and Measurements Analyst for Digital
Devices needs to develop a time standard for the task of assembling a computer
mouse. In a preliminary study, she observed one of her workers perform this
task six times with the following results:
127. What is the observed time (OT) for this
task?
A. 34 seconds
B. 40 seconds
C. 46 seconds
D. 48 seconds
E. 240 seconds
A. 34 seconds
B. 40 seconds
C. 46 seconds
D. 48 seconds
E. 240 seconds
128. What is the normal time (NT) for this task if the
employee worked at a 20% faster pace than is average?
A. 8 seconds
B. 32 seconds
C. 40 seconds
D. 48 seconds
E. 200 seconds
A. 8 seconds
B. 32 seconds
C. 40 seconds
D. 48 seconds
E. 200 seconds
129. What is the standard time (ST) for this task if
the employee worked at a 20% faster pace than is average and an allowance of
25% of the workday is used?
A. 40 seconds
B. 50 seconds
C. 53.3 seconds
D. 60 seconds
E. 64 seconds
A. 40 seconds
B. 50 seconds
C. 53.3 seconds
D. 60 seconds
E. 64 seconds
130. What is the standard time (ST) for this task if
the employee worked at a 20% faster pace than is average and an allowance of
25% of job time is used?
A. 40 seconds
B. 50 seconds
C. 53.3 seconds
D. 60 seconds
E. 64 seconds
A. 40 seconds
B. 50 seconds
C. 53.3 seconds
D. 60 seconds
E. 64 seconds
131. How many observations should be made if she wants
to be 0.8664 confident that the maximum error in the observed time is 0.5
second? Assume that the standard deviation of the task time is 4 seconds.
A. 10
B. 12
C. 120
D. 144
E. 169
A. 10
B. 12
C. 120
D. 144
E. 169
The manager of Lawn and Garden Services would like to
estimate the proportion of her employees' time spent performing various
gardening or lawn care activities. She has made 400 random observations of a
typical worker, with the following results:
132. What is the most likely true proportion of time
spent mowing?
A. 0
B. .1
C. .2
D. .5
E. 1
A. 0
B. .1
C. .2
D. .5
E. 1
133. What is the probability that the true proportion
of time spent mowing is exactly equal to the sample proportion?
A. 0
B. .1
C. .2
D. .5
E. 1
A. 0
B. .1
C. .2
D. .5
E. 1
134. How confident can the manager be that the true
proportion of time spent mowing is between .45 and .55?
A. 90 percent
B. 95 percent
C. 95.5 percent
D. 99 percent
E. 99.7 percent
A. 90 percent
B. 95 percent
C. 95.5 percent
D. 99 percent
E. 99.7 percent
135. Between what limits can the manager be 68.26
percent confident the true proportion of time spent mowing is?
A. 0 and .683
B. .475 and .525
C. .45 and .55
D. .425 and .575
E. .4 and .6
A. 0 and .683
B. .475 and .525
C. .45 and .55
D. .425 and .575
E. .4 and .6
136. If the manager wants to be 95.44 percent
confident that the true proportion of time spent mowing is within .02 (plus or
minus) of the sample proportion, what should be her sample size?
A. 400
B. 1,000
C. 1,600
D. 2,000
E. 2,500
A. 400
B. 1,000
C. 1,600
D. 2,000
E. 2,500
1. Location decisions are
basically one-time decisions usually made by new organizations.
True False
True False
2. The fact that most types of firms are located in
every section of the country suggests that in many cases, location decisions
are not overly important; one location typically is as good as another.
True False
True False
3. You can't make a mistake by locating where labor
costs are low.
True False
True False
4. Advanced communications has aided
globalization.
True False
True False
5. The first step in developing location alternatives
is identifying important factors.
True False
True False
6. An example of a regional factor in location
planning is the location of our markets (either existing or potential).
True False
True False
7. A strategy that emphasizes convenience for the
customers would probably select a single very large facility.
True False
True False
8. For service organizations,
the dominant factors in location analysis usually are market-related.
True False
True False
9. Global Positioning Systems (GPS) use the Center of
Gravity method to establish starting grid co-ordinates.
True False
True False
10. Labor laws are an important site-related
factor.
True False
True False
11. Web-based, retail businesses should be located
near the customer to reduce their long distance phone charges.
True False
True False
12. For service and retail stores, a prime factor in
location analysis is customer access.
True False
True False
13. Retail businesses generally prefer locations that
are not near other retailers, as this reduces their competition.
True False
True False
14. Technology has made communication with global
operations as easy as local communication.
True False
True False
15. Factor rating is limited to quantitative
information concerning location decisions.
True False
True False
16. As a result of the factor rating analysis, a
manager may sometimes reject all of the alternatives under consideration when
the composite scores are below the minimum threshold value.
True False
True False
17. The lower cost of foreign labor is often offset by
lower levels of productivity.
True False
True False
18. The center of gravity method is a location
planning technique that determines a composite score from weighted factor
evaluation.
True False
True False
19. The center of gravity method is useful in location
planning for the location of a distribution center.
True False
True False
20. The center of gravity method of location planning
is accurate only when the quantities to be shipped to each location are
equal.
True False
True False
21. Location decisions are closely tied to an organization's
strategies.
True False
True False
22. A "micro-factory" is a small, automated
facility with a narrow product focus located near major markets.
True False
True False
23. One of the reasons for the importance of location
decisions is its strategic importance to the supply chains.
True False
True False
24. Nearness to raw materials would be most important
to a ¼
A. grocery store
B. tax preparation service
C. manufacturing company
D. post office
E. hospital
A. grocery store
B. tax preparation service
C. manufacturing company
D. post office
E. hospital
25. A one-hour photo processing machine in a Wal-Mart
store is an example of a _________.
A. micro-factory
B. downsize strategy
C. diversified strategy
D. lean production system
E. falling price strategy
A. micro-factory
B. downsize strategy
C. diversified strategy
D. lean production system
E. falling price strategy
26. Which statement best characterizes a typical
search for location alternatives?
A. identify the best location choice
B. minimize cost consequences
C. maximize associated profits
D. locate near markets
E. identify acceptable locations
A. identify the best location choice
B. minimize cost consequences
C. maximize associated profits
D. locate near markets
E. identify acceptable locations
27. Which of the following is not a location option
that management can consider in location planning?
A. expand an existing facility
B. add a new location
C. relocate from one location to another
D. do nothing
E. All are possible options.
A. expand an existing facility
B. add a new location
C. relocate from one location to another
D. do nothing
E. All are possible options.
28. Which of the following is the last step in the
procedure for making location decisions?
A. determine the evaluation criteria
B. identify important factors
C. develop location alternatives
D. evaluate alternatives and make a selection
E. request input regarding alternatives
A. determine the evaluation criteria
B. identify important factors
C. develop location alternatives
D. evaluate alternatives and make a selection
E. request input regarding alternatives
29. When a location evaluation includes both
quantitative and qualitative inputs, a technique that can be used is ___________.
A. Linear programming
B. Consumer surveys
C. Factor rating
D. Transportation models
E. Center of gravity methods
A. Linear programming
B. Consumer surveys
C. Factor rating
D. Transportation models
E. Center of gravity methods
30. The center of gravity method is used to _______
travel time, distance and costs.
A. Normalize
B. Eliminate
C. Average
D. Minimize
E. Document
A. Normalize
B. Eliminate
C. Average
D. Minimize
E. Document
31. In location planning, the location of raw
materials, the location of markets, and labor factors are:
A. regional factors
B. community factors
C. site-related factors
D. national factors
E. minor considerations
A. regional factors
B. community factors
C. site-related factors
D. national factors
E. minor considerations
32. Software systems known as GIS help in location
analysis. The initials GIS stand for _______.
A. Graphic Interface Systems
B. Global Integrated Software
C. Graded Information Systems
D. Geo Intensive Software
E. Geographical Information System
A. Graphic Interface Systems
B. Global Integrated Software
C. Graded Information Systems
D. Geo Intensive Software
E. Geographical Information System
33. Facilities, personnel and operations that are
located around the world are called:
A. non-domestic
B. diversified operations
C. globalization
D. worldwide presence
E. virtual organization
A. non-domestic
B. diversified operations
C. globalization
D. worldwide presence
E. virtual organization
34. Some communities offer financial and other
incentives to ______ new businesses.
A. Tax
B. Attract
C. Marginalize
D. Incorporate
E. Zone
A. Tax
B. Attract
C. Marginalize
D. Incorporate
E. Zone
35. Location options don't usually include:
A. expansion
B. a contract
C. adding new facilities
D. moving
E. doing nothing
A. expansion
B. a contract
C. adding new facilities
D. moving
E. doing nothing
36. Cultural differences, Customer preferences, Labor
and Resources are factors relating to:
A. Regional choices
B. Site selection
C. Zoning
D. Product design
E. Foreign locations
A. Regional choices
B. Site selection
C. Zoning
D. Product design
E. Foreign locations
37. The method for evaluating location alternatives
which uses their total cost curves is:
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
38. The method for evaluating location alternatives
which minimizes shipping costs between multiple sending and receiving locations
is:
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
39. The method for evaluating location alternatives
which uses their composite (weighted-average) scores is:
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
A. cost-volume analysis
B. transportation model analysis
C. factor rating analysis
D. linear regression analysis
E. MODI analysis
40. An approach to location analysis that can include
both qualitative and quantitative considerations is:
A. location cost-volume
B. factor rating
C. transportation model
D. expected value (net present value)
E. financial analysis
A. location cost-volume
B. factor rating
C. transportation model
D. expected value (net present value)
E. financial analysis
41. A location analysis has been narrowed down to two
locations, Akron and Boston. The main factors in the decision will be the
supply of raw materials, which has a weight of .50, transportation cost, which
has a weight of .40, and labor cost, which has a weight of .10. The scores for
raw materials, transportation, and labor are for Akron 60, 80, and 70,
respectively; for Boston 70, 50, and 90, respectively. Given this information
and a minimum acceptable composite score of 75, we can say that the manager
should:
A. be indifferent between these locations
B. choose Akron
C. choose Boston
D. reject both locations
E. build a plant in both cities
A. be indifferent between these locations
B. choose Akron
C. choose Boston
D. reject both locations
E. build a plant in both cities
42. A manager must decide
between two location alternatives, Boston and Chicago. Boston would have annual
fixed costs of $70,000, transportation costs of $60 per unit, and labor and
material costs of $200 per unit. Chicago would have annual fixed costs of
$90,000, transportation costs of $40 per unit, and labor and material costs of
$170 per unit. Revenue will be $300 per unit.
(A) Which alternative would yield the higher profit for an annual demand of 3,000 units?
(B) Would the two locations yield the same profit at a certain volume? If so, at what volume would that be?
(A) Which alternative would yield the higher profit for an annual demand of 3,000 units?
(B) Would the two locations yield the same profit at a certain volume? If so, at what volume would that be?
43. A firm is trying to decide
between two location alternatives, Albany and Baltimore. Albany would result in
annual fixed costs of $60,000, labor costs of $7 per unit, material costs of
$10 per unit, transportation costs of $15 per unit, and revenue per unit of
$50. Baltimore would have annual fixed costs of $80,000, labor costs of $6 per
unit, material costs of $9 per unit, transportation costs of $14 per unit, and
revenue per unit of $48.
(A) At an annual volume of 9,000, which would yield the higher profit?
(B) At what annual volume would management be indifferent between the two alternatives in terms of annual profits?
(A) At an annual volume of 9,000, which would yield the higher profit?
(B) At what annual volume would management be indifferent between the two alternatives in terms of annual profits?
44. Given the information below
on scores of three location alternatives, which alternative would you
recommend? Why?
45. Determine the center of
gravity location for the destinations and shipping quantities shown below:
46. Determine the optimum
location for a distribution center to serve the following locations. Shipments
to each location will be approximately equal.
The Skulls, a student social
organization, has two different locations under consideration for constructing
a new chapter house. Skull's president, a POM student, estimates that due to
differing land costs, utility rates, etc., both fixed and variable costs would
be different for each of the proposed sites, as follows:
47. What would be total annual costs for the Alpha
Ave. location with twenty persons living there?
A. $5,400
B. $4,000
C. $5,000
D. $7,000
E. $9,000
A. $5,400
B. $4,000
C. $5,000
D. $7,000
E. $9,000
48. What would be total annual costs for either
location at the point of indifference?
A. $13,000
B. $13,350
C. $9,000
D. $17,000
E. $19,200
A. $13,000
B. $13,350
C. $9,000
D. $17,000
E. $19,200
49. If it is estimated that thirty persons will be
living in this new chapter house, which location should the Skulls
select?
A. Alpha Ave.
B. Beta Blvd.
C. either Alpha Ave. or Beta Blvd.
D. reject both Alpha Ave. nor Beta Blvd.
E. become a virtual organization
A. Alpha Ave.
B. Beta Blvd.
C. either Alpha Ave. or Beta Blvd.
D. reject both Alpha Ave. nor Beta Blvd.
E. become a virtual organization
50. If it is estimated that thirty persons will be
living in this new chapter house, what would be the Skull's annual cost savings
by selecting the less costly location, rather than the more costly?
A. $0
B. $1,500
C. $200
D. $150
E. $350
A. $0
B. $1,500
C. $200
D. $150
E. $350
51. What are total costs for
site A for a quantity of 5,000 units per year?
52. What are total costs for
site B for a quantity of 5,000 units per year?
53. What are total costs for
site C for a quantity of 5,000 units per year?
54. For what quantity would you
be indifferent between selecting site A or site B?
55. For what quantity would you
be indifferent between selecting site B or site C?
56. For what range of output
would you prefer site A?
57. For what range of output
would you prefer site B?
58. For what range of output
would you prefer site C?
59. Which site would you prefer
for a quantity of 20,000 units per year?
60. For the preferred site for
20,000 units per year, what would be your total costs?
61. For the preferred site for
20,000 units per year, what would be your cost savings compared to each of the
other two sites?
A manufacturing firm is
considering two locations for a plant to produce a new product. The two
locations have fixed and variable costs as follows:
62. At what annual output would the company be
indifferent between the two locations?
A. 60,000 units
B. 15,000 units
C. 10,000 units
D. 20,000 units
E. 4,000 units
A. 60,000 units
B. 15,000 units
C. 10,000 units
D. 20,000 units
E. 4,000 units
63. What would the total annual costs be for the
Phoenix location with an annual output of 10,000 units?
A. $280,000
B. $140,000
C. $220,000
D. $300,000
E. $156,000
A. $280,000
B. $140,000
C. $220,000
D. $300,000
E. $156,000
64. What would be the total annual costs at the point
of indifference?
A. $300,000
B. $240,000
C. $380,000
D. $220,000
E. $760,000
A. $300,000
B. $240,000
C. $380,000
D. $220,000
E. $760,000
65. If annual demand is estimated to be 20,000 units,
which location should the company select?
A. Atlanta
B. Phoenix
C. either Atlanta or Phoenix
D. reject both Atlanta and Phoenix
E. build at both locations
A. Atlanta
B. Phoenix
C. either Atlanta or Phoenix
D. reject both Atlanta and Phoenix
E. build at both locations
66. If the annual demand will be 20,000 units, what
would be the cost advantage of the better location?
A. $20,000
B. $460,000
C. $480,000
D. $80,000
E. $60,000
A. $20,000
B. $460,000
C. $480,000
D. $80,000
E. $60,000
A location analysis has been narrowed down to three
locations. The critical factors, their weights, and the ratings for each
location are shown below:
67. What is the composite score for location A?
A. 76
B. 75
C. 78
D. 74
E. 76.33
A. 76
B. 75
C. 78
D. 74
E. 76.33
68. What is the composite score for location B?
A. 76
B. 75
C. 78
D. 74
E. 76.33
A. 76
B. 75
C. 78
D. 74
E. 76.33
69. What is the composite score for location C?
A. 76
B. 75
C. 78
D. 74
E. 76.33
A. 76
B. 75
C. 78
D. 74
E. 76.33
70. If the selection criteria is to be the greatest
composite score, management should choose:
A. location A
B. location B
C. location C
D. either B or C
E. to reject all locations
A. location A
B. location B
C. location C
D. either B or C
E. to reject all locations
71. If the decisions rule is to select the location
with the greatest composite score exceeding 80, management should choose:
A. location A
B. location B
C. location C
D. either B or C
E. to reject all locations
A. location A
B. location B
C. location C
D. either B or C
E. to reject all locations
A clothing manufacturer produces clothing in five
locations in the U. S. In a move to vertical integration, the company is
planning a new fabric production plant that will supply fabric to all five
clothing plants. The clothing plants have been located on a coordinate system
as follows:
72. If the amount of fabric shipped to each plant is
equal, what is the optimal location for the fabric plant?
A. 5, 5
B. 6, 4
C. 4, 6
D. 6, 2
E. 5, 4
A. 5, 5
B. 6, 4
C. 4, 6
D. 6, 2
E. 5, 4
73. Shipments of fabric to each plant vary per week as
follows: plant A, 200 units; plant B, 400 units; plant C, 300 units; plant D,
300 units; and plant E, 200 units. What is the optimal location for the fabric
plant?
A. 6.2, 3.0
B. 6.0, 4.0
C. 6.5, 5.3
D. 5.6, 4.4
E. 5.0, 3.0
A. 6.2, 3.0
B. 6.0, 4.0
C. 6.5, 5.3
D. 5.6, 4.4
E. 5.0, 3.0
A hardware distributor has regional warehouses at the
locations shown below. The company wants to locate a new central distribution
center to serve this warehouse network.
74. If weekly shipments to each
warehouse will be approximately equal, what is the optimal location for the
distribution center?
A. 5, 5
B. 5, 4
C. 4, 5
D. 5, 6
E. 6, 5
A. 5, 5
B. 5, 4
C. 4, 5
D. 5, 6
E. 6, 5
75. Weekly shipments to each warehouse will be: WH1,
100; WH2, 150; WH3, 120; WH4, 150; and WH5, 120. What is the optimal location
of the distribution center?
A. 5.1, 4.2
B. 5.2, 4.0
C. 5.1, 5.1
D. 4.2, 5.1
E. 4.9, 5.2
A. 5.1, 4.2
B. 5.2, 4.0
C. 5.1, 5.1
D. 4.2, 5.1
E. 4.9, 5.2
76. Which of the following circumstances would be
least likely to lead to a need for a new location?
A. Shifting of markets.
B. Depletion of basic inputs.
C. Growth in demand that is leading to greater utilization of existing capacity.
D. The need to expand into new markets.
E. The opportunity to take advantage of globalization trends.
A. Shifting of markets.
B. Depletion of basic inputs.
C. Growth in demand that is leading to greater utilization of existing capacity.
D. The need to expand into new markets.
E. The opportunity to take advantage of globalization trends.
77. Which of the following is
least important as a consideration for a firm at the beginning of a supply
chain?
A. Access to end consumers
B. Access to resources
C. Proximity to customers
D. Access to transportation infrastructure
E. Access to productive labor
A. Access to end consumers
B. Access to resources
C. Proximity to customers
D. Access to transportation infrastructure
E. Access to productive labor
78. Location choice I has monthly fixed costs of
$100,000 and per-unit variable costs of $10. What would its total cost be at a
monthly volume of 250 units?
A. $105,200
B. $102,500
C. $100,250
D. $100,520
E. $105,500
A. $105,200
B. $102,500
C. $100,250
D. $100,520
E. $105,500
79. Location choice I has monthly fixed costs of
$100,000 and per-unit variable costs of $10. What would its total cost be at a
monthly volume of 550 units?
A. $105,200
B. $102,500
C. $100,250
D. $100,520
E. $105,500
A. $105,200
B. $102,500
C. $100,250
D. $100,520
E. $105,500
80. Location choice I has monthly fixed costs of
$100,000 and per-unit variable costs of $10. Location choice J has monthly
fixed costs of $150,000 and per-unit variable costs of $9. At what volume would
these locations have equal total costs?
A. 30,000 units
B. 25,000 units
C. 40,000 units
D. 50,000 units
E. 60,000 units
A. 30,000 units
B. 25,000 units
C. 40,000 units
D. 50,000 units
E. 60,000 units
No comments:
Post a Comment