Liberty
University BUSI 313 quiz 4 solutions answers right
How
many versions: 6 different versions
Question 1 Disadvantages of outsourcing
project work may likely include all of the following EXCEPT
Question 2 Experience indicates that colocation
of project teams is not worth the extra costs.
Question 3 When using the partnering approach
to manage contracted relationships, each party's goals and objectives are
similar but geared to what is best for them.
Question 4 Which of the following is true
in regard to negotiation when managing projects?
Question 5 Principled negotiation emphasizes
developing win/win solutions while protecting yourself against those who would
take advantage of your forthrightness. Which of the following is NOT one of the
key points of principled negotiation?
Question 6 A partnering charter states the
common goals for the project as well as the procedures that will be used to
achieve these goals.
Question 7 What does the acronym BATNA
stand for?
Question 8 When considering principled
negotiation, both buyers and sellers relying on the blue book to establish price
parameters of a used car would be an example of
Question 9 Jessica just received the
following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500,
EAC = 1208. In terms of cost at completion.
Question 10 Which of the following is NOT
true regarding scope creep?
Question 11 Because of their easytounderstand
visual format, tracking Gantt charts are the most favored, used, and
understandable option for reporting project status.
Question 12 The cost variance for a project
is calculated by
Question 13 A ___________ Gantt chart is a
simple and effective way to depict progress on a project.
Question 14 A project control system allows
for comparing actual performance against plan to identify deviations; however, the system doesn't impact the quality of communication
between stakeholders.
Question 15 Which of the following are
required to assess the current status of a project using the earnedvalue
cost/schedule system?
Question 16 A CPI or SPI value less than
one indicates that the project is
Question 17 Project closures can fall into
all of the following categories EXCEPT
Question 18 Assessing what fundamental
organizational culture properties affect project successes and failures, or
become a hindrance to project teams, is a part of the retrospectives
methodology.
Question 19 In organizations where projects
are managed within a ____________, the team member's area manager, not the
project manager, is responsible for assessing performance.
Question 20 Which part of the final report
is designed to be the most useful on future projects?
Question 21 During the closing phase, the
project manager's challenge is to keep the project team focused on the
remaining project activities and delivery to the customer until the project is
complete.
Question 22 Which of the following would
NOT be appropriate to assess when evaluating team performance?
Question 23 The final report typically
includes profit made on the project.
Question 24 A 360degree performance
evaluation includes feedback from peers, project managers, subordinates, and
even customers.
Question 25 Performance appraisals
generally fulfill two functions. The first is to identify individual strengths
and weaknesses and to develop action plans for improving performance. The
second involves salary or merit adjustments. Why should these two functions be
addressed at different times?
1. Contracting
project work has long been the norm in the _______ industry.
A. Telecommunications
B. Financial
C. Insurance
D. Construction
E. Retail
A. Telecommunications
B. Financial
C. Insurance
D. Construction
E. Retail
2. The process for the transferring of
business functions or processes to other, often foreign, companies has
traditionally been known as:
A. Subcontracting
B. Downsizing
C. Partnering
D. Joint venture
E. Outsourcing
A. Subcontracting
B. Downsizing
C. Partnering
D. Joint venture
E. Outsourcing
3. When you call your Internet provider to
solve a technical problem and you end up talking to a technician in India or
Romania, you have just experienced:
A. Telecommunications
B. Partnering
C. Outsourcing
D. Service shift
E. Bilingual customer service
A. Telecommunications
B. Partnering
C. Outsourcing
D. Service shift
E. Bilingual customer service
4. Which of the following is not a
potential part of the outsourcing concept?
A. Computers
B. Faxes
C. Computer-aided design systems
D. Video teleconferencing
E. All the above are correct
A. Computers
B. Faxes
C. Computer-aided design systems
D. Video teleconferencing
E. All the above are correct
5. Advantages of outsourcing project work
may likely include all of the following except
A. Shortened project completion
B. Reduced costs
C. Higher level of expertise
D. Reduced conflict
E. Increased flexibility
A. Shortened project completion
B. Reduced costs
C. Higher level of expertise
D. Reduced conflict
E. Increased flexibility
6. Disadvantages of outsourcing project
work may likely include all of the following except
A. Increased conflict
B. Coordination breakdowns
C. Increased costs
D. Loss of control
E. More internal morale issues
A. Increased conflict
B. Coordination breakdowns
C. Increased costs
D. Loss of control
E. More internal morale issues
7. The driving motive for increasing the
use of outsourcing on projects was:
A. Reducing the trade deficit
B. Reducing costs
C. Improving international sales
D. Making products more international in design
E. Securing technology that was not available domestically
A. Reducing the trade deficit
B. Reducing costs
C. Improving international sales
D. Making products more international in design
E. Securing technology that was not available domestically
8. Recent outsourcing trends have shown an
increasing emphasis on the suppliers for all of the following except:
A. Further cost reductions
B. Increased quality of work performed
C. Increased ability to collaborate
D. Increased ability to work together
E. All of these are recent trends
A. Further cost reductions
B. Increased quality of work performed
C. Increased ability to collaborate
D. Increased ability to work together
E. All of these are recent trends
9. Key practices in partnering
relationships include:
A. Single project contracting
B. Goals and objectives are similar
C. Access to each other's organizational resources
D. Both B and C are correct
E. A, B, and C are all correct
A. Single project contracting
B. Goals and objectives are similar
C. Access to each other's organizational resources
D. Both B and C are correct
E. A, B, and C are all correct
10. In the "Competing against the
Giants" Snapshot from Practice, SATT Control uses which of the following
to successfully compete against much larger competitors?
A. Excellent project management
B. Acts as a system integrator
C. Using the same subsystem vendors again and again
D. Both A and B are correct
E. A, B, and C are all correct
A. Excellent project management
B. Acts as a system integrator
C. Using the same subsystem vendors again and again
D. Both A and B are correct
E. A, B, and C are all correct
11. hich of the following is not a
key to successful partnering relationships?
A. Mutual trust
B. Jointly shared risk
C. Total company involvement
D. Independent project teams
E. Long-term commitment
A. Mutual trust
B. Jointly shared risk
C. Total company involvement
D. Independent project teams
E. Long-term commitment
12. Which of the following is part of the
traditional project process?
A. Structured communications
B. Long-term commitment
C. Total company involvement
D. Both A and B are correct
E. A, B, and C are all correct
A. Structured communications
B. Long-term commitment
C. Total company involvement
D. Both A and B are correct
E. A, B, and C are all correct
13. The traditional project process
includes all of the following except:
A. Independent project teams
B. Shared goals and objectives
C. Single project teams
D. Risk is transferred to the other party
E. Limited objectivity
A. Independent project teams
B. Shared goals and objectives
C. Single project teams
D. Risk is transferred to the other party
E. Limited objectivity
14. Which of the following did the state of
Ohio do before starting a bond-financed school construction project?
A. Create a specific RFP (request for proposal)
B. Have a dress rehearsal
C. Reviews the performance of contractors on past projects
D. Both A and C are correct
E. A, B, and C are all correct
A. Create a specific RFP (request for proposal)
B. Have a dress rehearsal
C. Reviews the performance of contractors on past projects
D. Both A and C are correct
E. A, B, and C are all correct
15. Best practices in outsourcing project
work include all the following except:
A. Well defined requirements and procedures
B. Training and teambuilding activities
C. Well established conflict management processes
D. Frequent reviews and status updates
E. All of these are best practices
A. Well defined requirements and procedures
B. Training and teambuilding activities
C. Well established conflict management processes
D. Frequent reviews and status updates
E. All of these are best practices
16. In the Snapshot from Practice
"Strategies for Communicating with Outsourcers," which of the
following was not one of the suggested strategies?
A. Recognize cultural differences
B. Use a translator to make sure everyone understands
C. Choose the right words
D. Confirm your requirements
E. Set deadlines
A. Recognize cultural differences
B. Use a translator to make sure everyone understands
C. Choose the right words
D. Confirm your requirements
E. Set deadlines
17. To make sure that an outsourcer
thoroughly understands your requirements you should:
A. Document your conversations in writing
B. Insist that the outsourcer write the requirements in their own words
C. Request they build a prototype
D. Both A and C are correct
E. A, B, and C are all correct
A. Document your conversations in writing
B. Insist that the outsourcer write the requirements in their own words
C. Request they build a prototype
D. Both A and C are correct
E. A, B, and C are all correct
18. The result of teambuilding among the
project's participants is a:
A. Signed contract
B. Legal partnership agreement
C. Project plan
D. Partnering charter
E. Responsibility matrix
A. Signed contract
B. Legal partnership agreement
C. Project plan
D. Partnering charter
E. Responsibility matrix
19. To avoid problems with schedules and
deadlines you should:
A. Develop detailed schedules
B. Hold frequent status reviews
C. Add a penalty clause to the contract
D. Hold frequent conversations with the outsourcer
E. Build extra time into the schedules that the outsourcer is not aware of
A. Develop detailed schedules
B. Hold frequent status reviews
C. Add a penalty clause to the contract
D. Hold frequent conversations with the outsourcer
E. Build extra time into the schedules that the outsourcer is not aware of
20. Among the many advantages for
establishing long-term partnerships are:
A. Reduced administrative costs
B. Improved performance
C. Improved communication
D. B and C are both correct
E. A, B, and C are all correct
A. Reduced administrative costs
B. Improved performance
C. Improved communication
D. B and C are both correct
E. A, B, and C are all correct
21. Long-term partnerships will provide all
the following except:
A. Improved communication
B. More efficient utilization of resources
C. Reduced need for total number of partnerships
D. Lower administrative costs
E. Improved innovation
A. Improved communication
B. More efficient utilization of resources
C. Reduced need for total number of partnerships
D. Lower administrative costs
E. Improved innovation
22. Teambuilding between partners
should:
A. Include engineers, architects, lawyers, specialists and other staff
B. Be facilitated by an outside consultant
C. Not take more than one day
D. A and B are both correct
E. A, B, and C are all correct
A. Include engineers, architects, lawyers, specialists and other staff
B. Be facilitated by an outside consultant
C. Not take more than one day
D. A and B are both correct
E. A, B, and C are all correct
23. Which of the following would be
included in best practices in outsourcing project work?
A. Establishing long-term relationships
B. Include financial incentives
C. Reduce costs by using tried and true methods
D. A and B are both correct
E. A, B, and C are all correct
A. Establishing long-term relationships
B. Include financial incentives
C. Reduce costs by using tried and true methods
D. A and B are both correct
E. A, B, and C are all correct
24. In the Snapshot from Practice dealing
with the Value Engineering Awards program, which branch of the U.S. government
was involved?
A. Department of Defense
B. Department of Commerce
C. Department of Transportation
D. N.A.S.A
E. Department of Education
A. Department of Defense
B. Department of Commerce
C. Department of Transportation
D. N.A.S.A
E. Department of Education
25. Which of the following is not
one of the key points of principled negotiation?
A. Use objective criteria when possible
B. Be honest and forthright
C. Focus on interests, not positions
D. Separate the people from the problem
E. Invent options for mutual gain
A. Use objective criteria when possible
B. Be honest and forthright
C. Focus on interests, not positions
D. Separate the people from the problem
E. Invent options for mutual gain
26. Customer satisfaction can be
quantitified by:
A. Perceived performance divided by actual performance
B. Actual performance divided by expected performance
C. Perceived performance divided by expected performance
D. Actual performance divided by perceived performance
E. Expected performance divided by actual performance
A. Perceived performance divided by actual performance
B. Actual performance divided by expected performance
C. Perceived performance divided by expected performance
D. Actual performance divided by perceived performance
E. Expected performance divided by actual performance
27. Which of the following is a part of the
noncompetitive view of negotiation?
A. Reaching an agreement
B. Implementation phase
C. Review of the completed project
D. Both A and B are correct
E. A, B, and C are all correct
A. Reaching an agreement
B. Implementation phase
C. Review of the completed project
D. Both A and B are correct
E. A, B, and C are all correct
28. Which of the following is suggested as
the best target for a customer satisfaction ratio?
A. 1.00
B. 1.05
C. 1.10
D. 1.20
E. 1.50
A. 1.00
B. 1.05
C. 1.10
D. 1.20
E. 1.50
29. In the research highlight on IT project
managers, which of the following was not one of the roles taken by project
managers?
A. Entrepreneur
B. Politician
C. Friend
D. Marketer
E. Auditor
A. Entrepreneur
B. Politician
C. Friend
D. Marketer
E. Auditor
30. Regarding customer relations, advice
passed on by veteran project managers includes:
A. Speak with one voice
B. Speak in precise terms
C. Speak the language of the customer
D. Both A and B are correct
E. Both A and C are correct
A. Speak with one voice
B. Speak in precise terms
C. Speak the language of the customer
D. Both A and B are correct
E. Both A and C are correct
31. Which of the following is not one of
the elements of good negotiation?
A. Be hard on the problem, soft on the people
B. Conflict on a project can be good
C. Negotiation is not a contest
D. Seek first to understand, then to be understood
E. All of these are elements of good negotiation
A. Be hard on the problem, soft on the people
B. Conflict on a project can be good
C. Negotiation is not a contest
D. Seek first to understand, then to be understood
E. All of these are elements of good negotiation
32. Which of the following is reflected in
the saying "Let anger fly out the window"?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
33. Which of the following is reflected in
the saying "Seek first to understand, then to be understood"?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
34. The dovetailing technique is used in which
of the following keys to good negotiation?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
35. Contracting
project work has long been the norm in the __________ industry.
36. The __________ project, which created a transportation tunnel between France and England, involved more than 250 organizations.
37. In a partnering relationship, ________ is shared jointly among the partners, which encourages innovation and continuous improvement.
38. In a partnering relationship, ________ forms the basis for strong working relationships.
39. In traditional project relationships, ________ is limited due to fear of reprisal and lack of continuous improvement opportunity.
40. In traditional project relationships, ________ are structured and guarded.
41. In Ohio before starting a bond-financed ____________, projects management consultants and the related parties get together to figure out how to talk to each others and how to handle problems.
42. The term __________ has traditionally been applied to the transferring of business functions or processes to other, often foreign, companies.
43. Many outsourced projects operate in a _________ environment in which people are linked by computers, faxes, computer-aided design systems, and video teleconferencing.
44. __________ is a major advantage of outsourcing project work because companies can secure competitive prices for contracted services, especially if the work can be outsourced offshore.
45. Not only can contracted project work be cheaper, it can also be done __________.
46. High levels of __________ and technology can be brought to bear on a project by using contracted services.
47. Contracting project services can increase a firm's _________ by no longer being constrained by their own resources.
48. Breakdowns in __________ of professionals from different organizations can occur if the project work requires close collaboration and mutual adjustment.
49. In the Snapshot from Practice involving SATT Control, a Swedish electronics firm, the company referred to one of its competencies as being a ________ who subcontracts the subsystems to other firms.
50. There is a potential loss of __________ over a project when the core team depends on other organizations that they do not have direct authority over.
51. Projects are more prone to interpersonal _________ because the different participants do not share the same values, priorities, and culture.
52. There is little disagreement that __________ was the primary motive behind outsourcing project work.
53. Fisher and Ury champion the ________ approach to negotiation because it emphasizes win/win solutions while protecting yourself against those who would take advantage of your forthrightness.
54. ________ satisfaction is measured by the ratio of perceived performance to expected performance.
55. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong __________.
56. As part of an effort to cut costs the United States Department of Defense issues annual __________.
57. "Let anger fly out of the window" is an example of the ___________ key point of negotiation.
58. Explaining why a critical task must be done by a specific time is an example of the ___________ key point of negotiation.
59. Dividing perceived performance by expected performance will calculate __________.
60. Toyota and Daimen-Chrysler collaborating with suppliers to develop new automobile platforms is an example of outsourcing.
61. Participants from different organizations working close together at the construction site or in shared office space is an example of a virtual team.
62. Working in outsourcing teams, projects can be completed faster and more cheaply.
63. Increased conflict and loss of coordination are typical disadvantages of outsourcing project work.
64. Trust can be difficult to forge when interactions are limited and people come from different organizations.
65. In partnering, access to each other's organization resources is available.
66. In the traditional method of managing projects, total company involvement requires commitment from CEO to team members.
67. In partnering, each party's goals and objectives are similar but geared to what is best for them.
68. As part of an effort to cut costs, the United States Department of Defense issues annual Value Engineering Awards.
69. In some countries, laws are considered to be guidelines that are not necessarily followed.
70. For people in some countries, a written, signed contract is merely a suggestion.
71. Because English is the language of business, it is not necessary to speak in a direct manner using short sentences made of basic, simple words as this may taken as an insult.
72. All conversations with outsourcers should be followed up with commitments documented in writing since they are likely to understand written English better than spoken English.
73. Experience indicates that co-location of project teams is not worth the extra costs.
74. A partnering charter states the common goals for the project as well as the procedures that will be used to achieve these goals.
75. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are often taken as a suggestion rather than a commitment.
76. A prime consideration in choosing outsourcing vendors is to assess the fit with their project management system.
77. Team-building workshops with outsourcing vendors is usually led by an outside consultant who is an expert in designing and facilitating such workshops.
78. In project negotiation each negotiator is out to win as much as he or she can for their side.
79. Principled Negotiation emphasizes developing win/win solutions while protecting yourself against those who would take advantage of your forthrightness.
80. By keeping the focus on the issues and not the personalities, negotiators are better able to let the other person blow off steam.
81. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong BATNA.
82. A value of 1.5 is the accepted target for the Met-Expectations model of customer satisfaction.
36. The __________ project, which created a transportation tunnel between France and England, involved more than 250 organizations.
37. In a partnering relationship, ________ is shared jointly among the partners, which encourages innovation and continuous improvement.
38. In a partnering relationship, ________ forms the basis for strong working relationships.
39. In traditional project relationships, ________ is limited due to fear of reprisal and lack of continuous improvement opportunity.
40. In traditional project relationships, ________ are structured and guarded.
41. In Ohio before starting a bond-financed ____________, projects management consultants and the related parties get together to figure out how to talk to each others and how to handle problems.
42. The term __________ has traditionally been applied to the transferring of business functions or processes to other, often foreign, companies.
43. Many outsourced projects operate in a _________ environment in which people are linked by computers, faxes, computer-aided design systems, and video teleconferencing.
44. __________ is a major advantage of outsourcing project work because companies can secure competitive prices for contracted services, especially if the work can be outsourced offshore.
45. Not only can contracted project work be cheaper, it can also be done __________.
46. High levels of __________ and technology can be brought to bear on a project by using contracted services.
47. Contracting project services can increase a firm's _________ by no longer being constrained by their own resources.
48. Breakdowns in __________ of professionals from different organizations can occur if the project work requires close collaboration and mutual adjustment.
49. In the Snapshot from Practice involving SATT Control, a Swedish electronics firm, the company referred to one of its competencies as being a ________ who subcontracts the subsystems to other firms.
50. There is a potential loss of __________ over a project when the core team depends on other organizations that they do not have direct authority over.
51. Projects are more prone to interpersonal _________ because the different participants do not share the same values, priorities, and culture.
52. There is little disagreement that __________ was the primary motive behind outsourcing project work.
53. Fisher and Ury champion the ________ approach to negotiation because it emphasizes win/win solutions while protecting yourself against those who would take advantage of your forthrightness.
54. ________ satisfaction is measured by the ratio of perceived performance to expected performance.
55. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong __________.
56. As part of an effort to cut costs the United States Department of Defense issues annual __________.
57. "Let anger fly out of the window" is an example of the ___________ key point of negotiation.
58. Explaining why a critical task must be done by a specific time is an example of the ___________ key point of negotiation.
59. Dividing perceived performance by expected performance will calculate __________.
60. Toyota and Daimen-Chrysler collaborating with suppliers to develop new automobile platforms is an example of outsourcing.
61. Participants from different organizations working close together at the construction site or in shared office space is an example of a virtual team.
62. Working in outsourcing teams, projects can be completed faster and more cheaply.
63. Increased conflict and loss of coordination are typical disadvantages of outsourcing project work.
64. Trust can be difficult to forge when interactions are limited and people come from different organizations.
65. In partnering, access to each other's organization resources is available.
66. In the traditional method of managing projects, total company involvement requires commitment from CEO to team members.
67. In partnering, each party's goals and objectives are similar but geared to what is best for them.
68. As part of an effort to cut costs, the United States Department of Defense issues annual Value Engineering Awards.
69. In some countries, laws are considered to be guidelines that are not necessarily followed.
70. For people in some countries, a written, signed contract is merely a suggestion.
71. Because English is the language of business, it is not necessary to speak in a direct manner using short sentences made of basic, simple words as this may taken as an insult.
72. All conversations with outsourcers should be followed up with commitments documented in writing since they are likely to understand written English better than spoken English.
73. Experience indicates that co-location of project teams is not worth the extra costs.
74. A partnering charter states the common goals for the project as well as the procedures that will be used to achieve these goals.
75. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are often taken as a suggestion rather than a commitment.
76. A prime consideration in choosing outsourcing vendors is to assess the fit with their project management system.
77. Team-building workshops with outsourcing vendors is usually led by an outside consultant who is an expert in designing and facilitating such workshops.
78. In project negotiation each negotiator is out to win as much as he or she can for their side.
79. Principled Negotiation emphasizes developing win/win solutions while protecting yourself against those who would take advantage of your forthrightness.
80. By keeping the focus on the issues and not the personalities, negotiators are better able to let the other person blow off steam.
81. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong BATNA.
82. A value of 1.5 is the accepted target for the Met-Expectations model of customer satisfaction.
1. A project monitoring system
involves all of the following EXCEPT
A. Determining what data to collect
B. Determining how, when, and who will collect the data
C. Adjusting the data
D. Analysis of the data
E. Reporting current progress
A. Determining what data to collect
B. Determining how, when, and who will collect the data
C. Adjusting the data
D. Analysis of the data
E. Reporting current progress
2. Nancy
tells her supervisor that as of right now, $1.05 worth of work has been
accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the
A. SV
B. TCPI
C. CPI
D. SPI
E. PCIB
B. TCPI
C. CPI
D. SPI
E. PCIB
3. Jessica
just received the following information on her project: PV = 200, EV = 300, AC =
250, BAC = 1500, EAC = 1208. In terms of
cost at completion
A. The project will currently
finish under budget
B. The project will currently finish over budget
C. The project will currently finish on budget
D. The project will currently finish behind schedule
E. There is insufficient information to draw conclusions
B. The project will currently finish over budget
C. The project will currently finish on budget
D. The project will currently finish behind schedule
E. There is insufficient information to draw conclusions
4. The
first step in the project control process for measuring and evaluating project
performance is to
A. Set a baseline plan
B. Determine the project objectives
C. Determine the project deliverables
D. Analyze the project budget
E. Review the project priority matrix
A. Set a baseline plan
B. Determine the project objectives
C. Determine the project deliverables
D. Analyze the project budget
E. Review the project priority matrix
5. The
second step in the project control process for measuring and evaluating project
performance is to
A. Review the baseline plan with top management
B. Analyze inputs to control system
C. Compare plan against actual
D. Measure progress and performance
E. Review spending with team members
A. Review the baseline plan with top management
B. Analyze inputs to control system
C. Compare plan against actual
D. Measure progress and performance
E. Review spending with team members
6. The
third step in the project control process for measuring and evaluating project
performance is to
A. Review the baseline plan with top management
B. Analyze inputs to the control system
C. Compare the plan against actual performance
D. Measure both progress and performance
E. Review spending with team members
A. Review the baseline plan with top management
B. Analyze inputs to the control system
C. Compare the plan against actual performance
D. Measure both progress and performance
E. Review spending with team members
7. The final step in the project control process
for measuring and evaluating project performance is to
A. Take appropriate action
B. Prepare a report to top management
C. Follow up on corrective action
D. Measure progress and performance
E. Review spending with team members
B. Prepare a report to top management
C. Follow up on corrective action
D. Measure progress and performance
E. Review spending with team members
8. In
monitoring project time (schedule) performance, actual performance should be
compared to
A. Budgets for the current year
B. Top management's targets
C. Project network schedule derived from the WBS/OBS
D. Progress on similar past projects
E. Previous status reports
A. Budgets for the current year
B. Top management's targets
C. Project network schedule derived from the WBS/OBS
D. Progress on similar past projects
E. Previous status reports
9. A
___________ Gantt chart is a simple and effective way to depict progress on a
project. A. Baseline
B. Control
C. Variance
D. Tracking
E. Simple
B. Control
C. Variance
D. Tracking
E. Simple
10. A
tool used to monitor past project schedule performance and current performance,
and to estimate future schedule trends is a simple line chart known as a
A. Project schedule control chart
B. Gantt chart
C. PERT chart
D. Network diagram
E. Milestone chart
A. Project schedule control chart
B. Gantt chart
C. PERT chart
D. Network diagram
E. Milestone chart
11. The
earned value system starts with the time-phased costs that provide the project
baseline, which is called the
A. Planned budgeted value of
work scheduled
B. Planned budgeted value of work completed
C. Earned value of work scheduled
D. Scheduled value of work scheduled
E. Scheduled value of work completed
B. Planned budgeted value of work completed
C. Earned value of work scheduled
D. Scheduled value of work scheduled
E. Scheduled value of work completed
12. The
earned value of a project is the
A. Project cost to date adjusted for project scope changes
B. Total project cost to date
C. Cost incurred minus the planned cost
D. Percent of the original budget that has been earned by actual work
E. The planned time-phased baseline of the value of work scheduled
A. Project cost to date adjusted for project scope changes
B. Total project cost to date
C. Cost incurred minus the planned cost
D. Percent of the original budget that has been earned by actual work
E. The planned time-phased baseline of the value of work scheduled
13. The
cost variance for a project is calculated by
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EU - PV
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EU - PV
14. The
schedule variance for a project is calculated by:
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EV - PV
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EV - PV
15. Baseline
project budgets are derived from
A. The organization's overall budget
B. Time-phasing the work packages
C. Top management directions
D. The total direct, direct project overhead and G&A overhead costs
E. The earned value system
A. The organization's overall budget
B. Time-phasing the work packages
C. Top management directions
D. The total direct, direct project overhead and G&A overhead costs
E. The earned value system
16. Of
the following costs, which are NOT included in baseline?
A. Suppliers
B. Equipment
C. Labor
D. Budget reserves
E. Contractors
A. Suppliers
B. Equipment
C. Labor
D. Budget reserves
E. Contractors
17. When
someone familiar with each task estimates what percent of the task has been
completed or how much of the task remains, they are creating a method for
assigning costs to the baseline called the
A. 0/100 percent rule
B. Task complete rule
C. Degree complete rule
D. Work complete rule
E. Percent complete rule
A. 0/100 percent rule
B. Task complete rule
C. Degree complete rule
D. Work complete rule
E. Percent complete rule
18. Which
performance index is the most potentially misleading?
A. CPI
A. CPI
B. EV
C. CV
D. SV
E. EAC
C. CV
D. SV
E. EAC
19. Which
of the following are required to assess the current status of a project using
the earned-value cost/schedule system?
A. BAC, EAC, and ETC
B. VAC, EAC, and BAC
C. CV, SU, and BAC
D. PV, EV, and AC
E. TCPI, EV, and PV
A. BAC, EAC, and ETC
B. VAC, EAC, and BAC
C. CV, SU, and BAC
D. PV, EV, and AC
E. TCPI, EV, and PV
20. Which
of the following methods of variance analysis is the best indicator of how far
off the budget a project will be at completion?
A. BAC
B. EAC
C. ETC
D. VAC
E. TCPI
A. BAC
B. EAC
C. ETC
D. VAC
E. TCPI
21. Which
of the following methods will measure the cost efficiency of the work
accomplished to date?
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
22. Which
of the following methods will measure the scheduling efficiency of the
work accomplished to date?
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
23. A CPI
or SPI value less than one indicates that the project is
A. Under cost or behind schedule
B. Over cost or ahead of schedule
C. Under cost or ahead of schedule
D. Over cost or behind schedule
E. On cost or on schedule
A. Under cost or behind schedule
B. Over cost or ahead of schedule
C. Under cost or ahead of schedule
D. Over cost or behind schedule
E. On cost or on schedule
24. The
value that tells you the planned value of work that has actually been completed
is the
A. SV
B. PV
C. EV
D. AC
E. CV
A. SV
B. PV
C. EV
D. AC
E. CV
25. The
indicator that tells you the amount each remaining dollar must earn in order
for the project to stay within budget is the
A. PCIC
B. VAC
C. CPI
D. SPI
E. TCPI
B. VAC
C. CPI
D. SPI
E. TCPI
26. A
project manager learns that the project is only earning $.90 of planned work
for each dollar spent by looking at the
A. EV
B. BAC
C. SV
D. SPI
E. CPI
B. BAC
C. SV
D. SPI
E. CPI
27. A
project manager notices that $1,000 worth of work that was scheduled to be
completed at this time has not been accomplished. They know this by looking at the
A. EV
B. TCPI
C. SV
D. PCIB
E. EAC
B. TCPI
C. SV
D. PCIB
E. EAC
28. Sally receives the following information on her project: PV = 100,
AC = 75, EV = 100. How well is the
project doing in terms of budget?
A.
Right on budget
B. 25 under budget
C. 25 over budget
D. 50 under budget
E. 50 over budget
C. 25 over budget
D. 50 under budget
E. 50 over budget
29. Jim
receives the following information on his project: PV = 1000, EV = 1200, AC =
800, BAC = 2000, EAC = 1333. How is the
project doing in terms of schedule?
A. More work has been done than
planned
B. Less work has been done than planned
C. The same amount of work has been done than planned
D. The project has cost less than planned
E. There is not enough information to draw a conclusion
B. Less work has been done than planned
C. The same amount of work has been done than planned
D. The project has cost less than planned
E. There is not enough information to draw a conclusion
30. Which of the following is
NOT true regarding scope creep?
A. It commonly occurs late in projects
B. It is frequently unnoticed until time delays or cost overruns are observed
C. It wears down team motivation and cohesiveness
D. Project suppliers resent frequent changes
E. Scope changes can represent significant opportunity
A. It commonly occurs late in projects
B. It is frequently unnoticed until time delays or cost overruns are observed
C. It wears down team motivation and cohesiveness
D. Project suppliers resent frequent changes
E. Scope changes can represent significant opportunity
31. ________
holds people accountable, prevents small problems from mushrooming into large
problems, and keeps focus.
32. The first step in creating a project control system for measuring and evaluating project performance is to set a ________.
33. The value that tells you the planned value of the actual work completed is ___________.
32. The first step in creating a project control system for measuring and evaluating project performance is to set a ________.
33. The value that tells you the planned value of the actual work completed is ___________.
34. When
someone familiar with each task estimates what percent of the task has been
completed or how much of the task remains, they are creating a method for
assigning costs to the baseline called the ____________ rule.
35. Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.
36. The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
35. Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.
36. The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
37. Baseline
project budgets are derived from time-phasing the work ________.
38. The
________ variance is the difference between the earned value and the actual
costs for the work completed to date.
39. The ________ variance is the difference between the earned value to date and the baseline schedule.
40. ________ is simply the percent complete times the original budget.
41. Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information.
39. The ________ variance is the difference between the earned value to date and the baseline schedule.
40. ________ is simply the percent complete times the original budget.
41. Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information.
42. The
project network schedule is derived from the _______ and it serves as the
baseline to compare against actual performance.
43. A negative CV indicates the project is ________ budget.
44. The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.
43. A negative CV indicates the project is ________ budget.
44. The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.
45. The
ratio that measures the amount of value each remaining dollar in the budget
must earn to stay within the budget is the _________.
46. The
_________ index measures the project percent complete in relation to the
resources that were budgeted.
47. Given
that the AC = 300, PV = 400 and EV = 500, this project is _________
budget.
48. Given a BAC of 5,500 and an EAC of 6,000, the project is expected to be completed _________ budget.
48. Given a BAC of 5,500 and an EAC of 6,000, the project is expected to be completed _________ budget.
49. An
SPI index of 1.22 indicates that the project is ________ schedule.
50. Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.
51. The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.
52. In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.
53. The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
54. The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
50. Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.
51. The final step in the project control process for measuring and evaluating project performance is to take appropriate ________.
52. In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.
53. The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project.
54. The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time.
55. Schedule
variance measures progress in time units.
56. Earned
value is defined as the budgeted cost of the actual work performed.
57. The baseline is derived from merging information from the work packages with the project network.
58. Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.
59. The PV, AC and CV are all required to assess the current status of the project.
57. The baseline is derived from merging information from the work packages with the project network.
58. Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.
59. The PV, AC and CV are all required to assess the current status of the project.
60. When
revising the estimated cost at completion, there are two approaches. The EACre is determined by experts in the
field and the EACf is a mathematical approach which assumes the CPI as the
basis for forecasting cost at completion.
61. The
best method for assigning costs to the baseline under the 50/50 rule is to
establish frequent checkpoints over the duration of the work package and assign
completion percentages in dollar terms.
62. Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
62. Most changes will not result in serious scope changes and should be absorbed as positive or negative variances.
63. A
“rubber baseline” occurs when, in an effort to disguise poor performance, the
baseline changes to constantly match results.
64. Baseline
costs typically include labor, equipment, materials and direct overhead
cost.
65. A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn’t impact the quality of communication between stakeholders.
65. A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn’t impact the quality of communication between stakeholders.
66. Two
major reasons for creating a baseline are to monitor and report progress and to
estimate cash flow.
67. In
calculating schedule variance and cost variance, a negative variance indicates
a desirable condition, and a positive variance suggests problems.
68. An undesirable schedule variance always indicates that the project is running behind schedule.
69. Progress and performance can be measured quantitatively as well as qualitatively.
68. An undesirable schedule variance always indicates that the project is running behind schedule.
69. Progress and performance can be measured quantitatively as well as qualitatively.
70. A CPI
index of 0.97 indicates that the project has spent less money than budgeted.
71. Rachel notices that the current EV for her project is higher than both the PV and the AC. Rachel has reason to be concerned.
71. Rachel notices that the current EV for her project is higher than both the PV and the AC. Rachel has reason to be concerned.
72. All
scope changes that result in increased costs should be avoided.
73. Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.
74. Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.
75. A project manager would be glad to see a TCPI of 1.07.
76. A negative VAC indicates that the project will be completed over budget.
73. Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance.
74. Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system.
75. A project manager would be glad to see a TCPI of 1.07.
76. A negative VAC indicates that the project will be completed over budget.
1. The most common circumstance for project closure is
simply a ________ project.
A. Completed
B. Overdue
C. Over-budget
D. Underachieving
E. Successful
A. Completed
B. Overdue
C. Over-budget
D. Underachieving
E. Successful
2. Which of the following is NOT a wrap-up
closure activity that might be found on a checklist?
A. Getting delivery acceptance from the customer
B. Reassigning project team members
C. Closing accounts and seeing all bills are paid
D. Evaluation of team performance
E. Creating a final report
A. Getting delivery acceptance from the customer
B. Reassigning project team members
C. Closing accounts and seeing all bills are paid
D. Evaluation of team performance
E. Creating a final report
3. __________ of lessons learned are designed to
improve performance on current and future projects.
A. Retrospectives
B. Corrective action plans
C. Introspectives
D. Culminations
E. Evolutions
A. Retrospectives
B. Corrective action plans
C. Introspectives
D. Culminations
E. Evolutions
4. The
content of the final report typically includes the following topics
EXCEPT
A. Lessons learned
B. Review and analysis
C. Recommendations
D. Executive summary
E. Team reviews
A. Lessons learned
B. Review and analysis
C. Recommendations
D. Executive summary
E. Team reviews
5. When
the project may be completed early with some parts of the project eliminated
this is considered to be ___________ closure.
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
6. This
type of closure occurs when the project may never seem to end. At some point
the review group should recommend methods for bringing final closure to this
type of project. This is considered to be ___________ closure.
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
7. Because of
circumstances beyond the control of the project team, many projects are easy
for a review group to close down. This
type of project closure is called
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
8. When a
project starts with a high priority but it is cancelled because its rank erodes
or crashes during its project life cycle, this is an example of what type of
project closure?
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
9. Which
of the following summarizes project performance and provides useful information
for continuous improvement?
A. Customer acceptance
B. The final report
C. Team evaluation
D. 360-degree feedback
E. Project summary
B. The final report
C. Team evaluation
D. 360-degree feedback
E. Project summary
10. Which
part of the final report highlights the key findings and facts relating to the
project implementation?
A. Executive summary
B. Review and analysis
C. Recommendations
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
E. Appendix
11. Which
part of the final report examines in detail the underlying causes of problems,
issues, and successes relative to the project and includes concise, factual
review statements of the project?
A. Executive summary
B. Review and analysis
C. Recommendations
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
E. Appendix
12. Which
part of the final report presents major improvement actions that should be
made?
A. Executive summary
B. Review and analysis
C. Recommendations
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
E. Appendix
13. Which
part of the final report is designed to be the most useful on future projects?
A. Executive summary
B. Review and analysis
C. Recommendations
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
E. Appendix
14. Which
part of the final report includes backup data or details of analysis that would
allow others to follow up if they wished?
A. Executive summary
B. Review and analysis
C. Recommendations
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
E. Appendix
15. The
purpose of project evaluation is to assess how well
A. The project team performed
B. The team members performed
C. The project manager performed
D. The project team and team members performed
E. The project team, team members and the project manager performed
B. The team members performed
C. The project manager performed
D. The project team and team members performed
E. The project team, team members and the project manager performed
16. Which
of the following would NOT be appropriate to assess when evaluating team
performance?
A. How well the team
performed in terms of time, cost, and specifications
B. Effectiveness of group
decisions
C. Individual strengths and weaknesses
D. Customer satisfaction with project deliverables
E. Trust among group members
C. Individual strengths and weaknesses
D. Customer satisfaction with project deliverables
E. Trust among group members
17. Before
an evaluation of the project team can be effective and useful, a minimum core
of conditions needs to be in place before the project begins. Which of the following would NOT be
one of those conditions?
A. Individuals have the skillset necessary to successfully
complete the project
B. Evaluation criteria beyond time, cost and specifications has been established
C. Rewards are adequate
D. Individual and team responsibilities and performance standards are known by all team members
E. Standards for measuring performance exist
B. Evaluation criteria beyond time, cost and specifications has been established
C. Rewards are adequate
D. Individual and team responsibilities and performance standards are known by all team members
E. Standards for measuring performance exist
18. Performance
appraisals generally fulfill two functions.
The first is to identify individual strengths and weaknesses and to
develop action plans for improving performance.
The second involves salary or merit adjustments. Why should these two functions be addressed at different times?
A. It is too much information
to discuss at once
B. Employees are so eager to learn about a potential raise that
they tend to tune out constructive feedback
C. Managers tend to spend too much time talking about how the employee can improve his or her performance and not on justifying the salary adjustment
D. If employees are upset over a salary adjustment, they will not be open to listening to ways they can improve.
E. If the manager is giving employees bad news regarding their salary adjustment, they will not be honest about the employees’ weaknesses and will tend to focus on their strengths.
C. Managers tend to spend too much time talking about how the employee can improve his or her performance and not on justifying the salary adjustment
D. If employees are upset over a salary adjustment, they will not be open to listening to ways they can improve.
E. If the manager is giving employees bad news regarding their salary adjustment, they will not be honest about the employees’ weaknesses and will tend to focus on their strengths.
19. The
following are general tips for conducting performance reviews EXCEPT
A. Begin the process by
asking the individual to evaluate his or her own contributions to the project
B. Use other team members’ performance as a method to compare and evaluate
C. When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally
D. Be fair and consistent in your treatment of all team members
E. Treat the review as only one point in an ongoing process
B. Use other team members’ performance as a method to compare and evaluate
C. When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally
D. Be fair and consistent in your treatment of all team members
E. Treat the review as only one point in an ongoing process
20. An
analysis carried out during and shortly after the project life cycle that
attempts to capture positive and negative learning is
represented in which of the following?
A. Scenario analysis
B. Variance analyses
C. Lessons learned
D. Performance evaluation
E. Strategic objectives
B. Variance analyses
C. Lessons learned
D. Performance evaluation
E. Strategic objectives
21. The
process for capturing lessons learned continues to evolve, but there are still
many barriers to effectively capitalizing on lessons learned that have been
identified. The following are examples of these barriers EXCEPT
A. Lack of time
B. Teams get little direction or support after lessons are reported
C. Lessons learned often degenerate into blame sessions
D. Lessons learned are being used across different locations
E. The organizational culture doesn’t support the effort that it takes to capitalize on lessons learned
B. Teams get little direction or support after lessons are reported
C. Lessons learned often degenerate into blame sessions
D. Lessons learned are being used across different locations
E. The organizational culture doesn’t support the effort that it takes to capitalize on lessons learned
22. The following are
distinguishing characteristics of retrospectives methodology EXCEPT
A. Uses an independent
facilitator
B. Establishes in-process
learning gates during the project life cycle
C. An owner, typically a team member, is assigned
D. Reviews cannot be linked to percent complete
E. A repository is developed that is easy to use
C. An owner, typically a team member, is assigned
D. Reviews cannot be linked to percent complete
E. A repository is developed that is easy to use
23. Project
closures can fall into all of the following categories EXCEPT
A. Premature
B. Perpetual
C. Failed
D. Changed priority
E. Successful
A. Premature
B. Perpetual
C. Failed
D. Changed priority
E. Successful
24. A
guide who leads the project team through an analysis of project activities that
went well and of what needs improvement and development of a follow-up action
plan with goals and accountability is a(n)
A. Owner
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
25. It is imperative that the closure facilitator possess the
following characteristics EXCEPT
A. Has direct involvement or direct interest in the project
B. Is perceived as impartial and fair
C. Has respect for senior management and other project stakeholders
D. Willing to listen
E. Is perceived as having the best interests of the organization in making decisions
C. Has respect for senior management and other project stakeholders
D. Willing to listen
E. Is perceived as having the best interests of the organization in making decisions
26. The typical mechanism for
the evaluation of teams is normally
A. A survey completed by the team members
B. A personal interview of each team member
C. An analysis by an outside consultant
D. A survey completed by members of top management
E. A survey completed by the internal or external customers
A. A survey completed by the team members
B. A personal interview of each team member
C. An analysis by an outside consultant
D. A survey completed by members of top management
E. A survey completed by the internal or external customers
27. More
and more companies are discarding the traditional superior-subordinate
performance feedback process and replacing it with a multi-rater appraisal
called
A. Critical incidences review
B. Management by objectives
C. The 360-degree feedback
D. Team evaluation survey
E. Retrospectives
A. Critical incidences review
B. Management by objectives
C. The 360-degree feedback
D. Team evaluation survey
E. Retrospectives
28. Which
of the following is NOT a role of the closure facilitator?
A. Create an environment in
which stakeholders feel safe to provide input
B. Lead the team in exploring new ways for solving problems
C. Use several questionnaires as a starting point to conduct the post-project retrospective
B. Lead the team in exploring new ways for solving problems
C. Use several questionnaires as a starting point to conduct the post-project retrospective
D. Get delivery acceptance
from the customer
E. Elicit a 360-degree view and input from all stakeholders to create a more complete picture of project issues
E. Elicit a 360-degree view and input from all stakeholders to create a more complete picture of project issues
29. In
organizations where projects are managed within a ____________, the team
member's area manager, not the project manager, is responsible for assessing
performance.
A. Functional organization
B. Matrix organization
C. Flat organization
D. Project organization
E. Strong organization
A. Functional organization
B. Matrix organization
C. Flat organization
D. Project organization
E. Strong organization
30. Each
retrospective is assigned a(n) _________, typically a team member who is very
interested in and familiar with the retrospective. This individual will serve as the contact
point for anyone needing information relating to the retrospective.
A. Owner
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
31. ________
project closure is the most common circumstance for project closure and is
simply a completed project.
32. When a project is completed early with some parts of the project eliminated this is known as _________ project closure.
33. A ____________ project closure is usually easy to identify and easy for a review group to close down.
34. Projects in process may need to be altered or canceled. Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change. This is called __________project closure.
35. When the review group recommends methods for bringing final closure to a project that never seems it will end, this is an example of a ________ project closure.
32. When a project is completed early with some parts of the project eliminated this is known as _________ project closure.
33. A ____________ project closure is usually easy to identify and easy for a review group to close down.
34. Projects in process may need to be altered or canceled. Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change. This is called __________project closure.
35. When the review group recommends methods for bringing final closure to a project that never seems it will end, this is an example of a ________ project closure.
36. Within
the final report, a summary that simply highlights the key findings and facts
relating to project implementation is called the ___________ summary.
37. Implementing the closure process includes several _______ activities, including getting delivery acceptance from the customer.
37. Implementing the closure process includes several _______ activities, including getting delivery acceptance from the customer.
38. The
________ section of the final project report includes concise, factual review
statements of the project, such as project mission and objectives, procedures
and systems used, and organizational resources used.
39. Perhaps the_________ section of the final report is the most valuable contribution of the closure process.
40. The ________ section of the final project report is often technical in nature and focuses on solutions to problems that surfaced.
41. Within the final report, the ___________ may include backup data or details of analysis that would allow others to follow up if they wish.
42. The purpose of project __________ is to assess how well the project team, team members, and project manager performed.
39. Perhaps the_________ section of the final report is the most valuable contribution of the closure process.
40. The ________ section of the final project report is often technical in nature and focuses on solutions to problems that surfaced.
41. Within the final report, the ___________ may include backup data or details of analysis that would allow others to follow up if they wish.
42. The purpose of project __________ is to assess how well the project team, team members, and project manager performed.
43.
____________ of performance is essential to encourage changes in behavior and
to support individual career development and continuous improvement through
organizational learning.
44. The
________ feedback approach gathers anonymous feedback solicited from others
that is compared with the individual's self-evaluations.
45. The
typical mechanism for evaluation of teams is a ________ administered by a
consultant.
46. The
retrospective approach stresses gathering _____________ during project
execution and using them to change remaining work.
47. In organizations where projects are managed within a functional organization, the team member’s __________ manager is responsible for assessing performance.
47. In organizations where projects are managed within a functional organization, the team member’s __________ manager is responsible for assessing performance.
48. The
most common reason given for not creating lessons learned is the lack of
_________.
49. A ________ is a methodology that analyzes a past project event to determine what worked and what didn't, develop lessons learned, and create an action plan that ensures lessons learned are used to improve management of future projects.
50. Retrospective reviews should be set up in the project ___________ stage.
51. The ____________ report summarizes project performance and provides useful information for continuous improvement.
49. A ________ is a methodology that analyzes a past project event to determine what worked and what didn't, develop lessons learned, and create an action plan that ensures lessons learned are used to improve management of future projects.
50. Retrospective reviews should be set up in the project ___________ stage.
51. The ____________ report summarizes project performance and provides useful information for continuous improvement.
52. A
guide who leads the project team through an analysis of project activities that
went well and of what needs improvement and development of a follow-up action
plan with goals and accountability is known as a project ____________.
53. __________ represent an analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning.
54. Each retrospective is assigned a(n) __________, typically a team member who is very interested in and familiar with the retrospective.
53. __________ represent an analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning.
54. Each retrospective is assigned a(n) __________, typically a team member who is very interested in and familiar with the retrospective.
55. Motivation
can be the chief challenge when wrapping up closure activities. 56. In
premature project closure, the project may be completed early with some parts
of the project eliminated.
57. Retrospectives of lessons learned are designed to improve performance on current and future projects.
58. When a project starts as a high priority but its rank erodes or crashes during its project life cycle resulting in closure of the project, this is an example of changed priority project closure.
59. The final report typically includes profit made on the project.
60. The project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.
61. Implementing project closure includes getting delivery acceptance from the customer.
62. Within the final report, the project summary is the summary that simply highlights the key findings and facts relating to the project implementation.
63. Expectations, standards, supportive organizational culture, and constraints must be in place before project implementation; if not, the effectiveness of the evaluation process will suffer.
57. Retrospectives of lessons learned are designed to improve performance on current and future projects.
58. When a project starts as a high priority but its rank erodes or crashes during its project life cycle resulting in closure of the project, this is an example of changed priority project closure.
59. The final report typically includes profit made on the project.
60. The project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.
61. Implementing project closure includes getting delivery acceptance from the customer.
62. Within the final report, the project summary is the summary that simply highlights the key findings and facts relating to the project implementation.
63. Expectations, standards, supportive organizational culture, and constraints must be in place before project implementation; if not, the effectiveness of the evaluation process will suffer.
64. Evaluation
of performance is essential to encourage changes in behavior and to support
individual career development and continuous improvement through organizational
learning.
65. The
processes for capturing lessons learned continue to evolve, but there are still
barriers to effectively mining lessons learned.
66. Project
managers should wait to give feedback to the project team and team members
until the project has been completed.
Giving feedback throughout the project can distract project teams.
67. Assessing
what fundamental organizational culture properties affect project successes and
failures, or become a hindrance to project teams, is a part of the
retrospectives methodology.
68. In
organizations where projects are managed within a functional organization, the
team member’s area manager, not the project manager, is responsible for
assessing performance.
69. The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system.
70. A project closure where the project is completed early with some parts of the project eliminated would be classified as a failed project.
71. The key requirement in selection of the facilitator is one who is the end-user.
72. The retrospective facilitator should be able to deliver bad news to the project sponsor or senior management without recriminations.
69. The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system.
70. A project closure where the project is completed early with some parts of the project eliminated would be classified as a failed project.
71. The key requirement in selection of the facilitator is one who is the end-user.
72. The retrospective facilitator should be able to deliver bad news to the project sponsor or senior management without recriminations.
73. Retrospective
methodology is one positive step toward ensuring lessons learned are developed
and implemented.
74. A
360-degree performance evaluation includes feedback from peers, project
managers, subordinates, and even customers.
75. Project managers should, when possible, draw comparisons to other team members when conducting individual team member reviews.
76. The retrospective methodology is more inclusive and disciplined than past lessons learned approaches.
75. Project managers should, when possible, draw comparisons to other team members when conducting individual team member reviews.
76. The retrospective methodology is more inclusive and disciplined than past lessons learned approaches.
No comments:
Post a Comment