Liberty
University BUSI 313 quiz 3 solutions answers right
How
many versions: 4 different versions
Question 1 The attempt to recognize and
manage potential and unforeseen trouble spots that may occur when a project is
implemented is known as
Question 2 Enhancing a risk is a tactic
that seeks to eliminate the uncertainty associated with an opportunity to
ensure that it definitely happens.
Question 3 Fixedprice contracts are an
example of transferring risk from an owner to a contractor.
Question 4 Which of the following is NOT
included in a Failure Mode and Effects Analysis?
Question 5 After your team has successfully
identified potential risks that could affect the project, what is the next
step?
Question 6 Adopting proven technology
instead of experimental technology is an example of mitigating a risk.
Question 7 If, during risk response
development, you successfully identify how you will respond to a risk,
contingency planning is unnecessary.
Question 8 The probability that a risk
event will occur is higher during the initial stages of a project.
Question 9 Regina's boss has told her that
her project is very important. If the critical path is delayed, she will be
given whatever she needs to get it back on schedule. Her project is classified
as ________ constrained.
Question 10 Gene is trying to order the
concrete needed to continue his project. However, the supplier will not be able
to deliver it until next week. This is an example of what kind of resource
constraint?
Question 11 Rachel is working on a project
that technically allows three activities to be done at the same time. If they
were to be implemented at the same time, she would need 5 contractors in order
for the activities to be completed on time. There are only 3 available for her
to use. This is an example of what type of constraint?
Question 12 Project budgets are developed
by timephasing which of the following?
Question 13 If resources are truly limited
and activity time estimates are accurate, the resourceconstrained schedule will
materialize as the project is implemented, not the timeconstrained schedule.
Question 14 When resource constraints are
added to technical constraints the original project network may change as well
as the completion date.
Question 15 In a resourceconstrained
project, the first priority in assigning resources is usually given to activities
with the
Question 16 Sequential activities hold just
as much potential for resource conflicts as parallel activities.
Question 17 These are all guidelines a
project manager should consider when assigning project work EXCEPT
Question 18 The higher the cost slope of an
activity the lower the cost to reduce its duration.
Question 19 One of the advantages of using
a Project CostDuration Graph is that it keeps the importance of indirect costs
in the forefront of decision making.
Question 20 When reducing project duration,
there will always be an optimum costtime point where the total cost of the
project is less than it was when the project was initially planned under normal
conditions.
Question 21 When reducing project duration,
the crash cost per unit has to be calculated and the maximum units each
activity can be reduced must be known. After this, the critical path must be
identified. What is the next step?
Question 22 The cost slope of an activity
is calculated by dividing the run by the rise.
Question 23 According to Brooks' Law,
adding more people to a late project is most likely to have which of the
following impacts?
Question 24 Reducing project duration
Question 25 As a project is crashed and
project duration is reduced, direct costs typically
An uncertain event or condition that, if
it occurs, has a positive or negative effect on project objectives is termed a
The chances of a risk event occurring as a
project proceeds through its life cycle tend to
The cost impact of a risk event occurring
as a project proceeds through its life cycle tends to
The attempt to recognize and manage
potential and unforeseen trouble spots that may occur when a project is
implemented is known as
Which of the following is NOT one of the
steps in the risk management process
The initial step in the risk management
process is to
One common mistake made early in the risk
identification process is to
Organizations use ____ in conjunction with
work breakdown structures to help management teams identify and eventually
analyze risk
Which of the following groups should NOT
be a part of the risk identification process?
After your team has successfully
identified potential risks that could affect the project, what is the next step
A list of questions that address
traditional areas of uncertainty on a project is termed a
____ focuses on how to respond to events
that have a positive impact on a project
Tools such as a risk assessment form and a
risk severity matrix are used to
Based on the following, which event should
you be most concerned about
____ is a measure of how easy it would be
to notice that a risk event was going to occur in time to take mitigating
action, that is, how much warning you would have
Purchasing an accident insurance policy
would be an example of responding to a risk by ____ it
The risk management tool that is divided
into three color-coded zones representing major, moderate, and minor risks is
the risk
The risk assessment form contains all of
the following EXCEPT
Risks are evaluated in terms of
Adopting proven technology instead of
experimental technology in order to eliminate technical failure would be an
example of which risk response
Which of the following activities might
you consider adding a time buffer to
Which of the following is NOT included in
a Failure Mode and Effects Analysis
A fixed price contract is an example of
Which of the following is NOT one of the
potential responses to a specific risk event
A Risk Response Matrix contains all of the
following EXCEPT
A key distinction between a risk response
and a contingency plan is
The risk associated with the unlikelihood
that one of the key members will be struck by lightning would most likely be
handled by which of the following
Funds that are for identified risks that
have a low probability of occurring and that decrease as the project progresses
are called ______ reserves
Risks that can result in a system or
process that will not work are known as
Which of the following is NOT involved in
risk control
Which of the following is identified to
cover major unforeseen risks and, hence, are applied to the total project
Change management systems are designed to
accomplish all of the following EXCEPT
An uncertain event or condition that, if
it occurs, has a positive or negative effect on project objectives is known as
a ____
The likelihood of a risk event occurring
____ as a project goes through its life cycle
The first step in the risk management
process is ____
The significance of a risk is assessed in
terms of the ____ and the impact of the event
A list of questions that address
traditional areas of uncertainty on a project is known as a
The measurement of how easy it would be to
detect that the event was going to occur in time to take mitigating action is
known as
The ____ form identifies each risk event,
the likelihood of it occurring, the potential impact, when it may occur, and
the degree of difficulty in detecting it
The ____ matrix is divided into red,
yellow, and green zones representing major, moderate, and minor risks
According to the Failure Mode and Effects
Analysis (FMEA), Impact x Probability x Detection = ____
When considering risk response
development, reducing the likelihood that an event will occur and/or reducing
the impact that an adverse event would have on a project is known as ____ the
risk
When considering risk response
development, changing the plan to eliminate the risk or condition is known as
____ the risk
When considering risk response
development, passing risk to another party instead of changing it is known as
____ the risk
When considering risk response
development, assuming the risk because the chance of such an event is slim is
known as ____ the risk
Testing a new project on a smaller
isolated area prior to installing it for the entire organization is an example
of ____ a risk
Performance bonds, warranties, and
insurance are examples of ____ a risk
Choosing to move a concert indoors to
eliminate the threat of bad weather is an example of ____ a risk.
Flooding would be devastating to the
project; however, it is very unlikely. The project manager is most likely to
____ this risk
The event or point in time when a
contingency plan will be implemented is called a ____
____ reserves are identified for specific
work packages and are distributed by the project manager and the team members.
____ reserves are controlled by the
project manager and the owner of the project and are used to cover major
unforeseen risks to the entire project
A ____ is an alternative that will be used
if a possible foreseen risk event becomes a reality
____ systems involve reporting,
controlling, and recording changes to the project baseline
The probability that a risk event will
occur is higher during the initial stages of a project
Risk events that occur in the early stages
of a project will have a greater cost impact than those that occur in later
stages
Risk management is a reactive approach
that is designed to ensure that surprises are reduced and that negative
consequences associated with undesirable events are minimized
One common mistake that is made early on
in the risk identification process is to focus on consequences and not on the
events that could produce consequences
The project being delayed is an example of
a major risk that should be assessed
The first step in the risk management
process is risk assessment
A risk profile is a list of questions that
have been developed and refined from previous, similar projects
The risk identification process should be
limited to just the core project team.
While a "can do" attitude is essential
during implementation, project managers have to encourage critical thinking
when it comes to risk identification
Responses to all identifiable risks should
be a top priority for the project manager
When considering risk value, the lower the
value, the higher the level of risk
If, during risk response development, you
successfully identify how you will respond to a risk, contingency planning is
unnecessary
Adopting proven technology instead of
experimental technology is an example of mitigating a risk
A risk is an uncertain event that, if it
occurs, can have a positive or negative effect on project objectives
Performance bonds, warranties, and
guarantees are financial instruments used to share risk.
Fixed-price contracts are an example of
transferring risk from an owner to a contractor
When developing a response to a risk by
scheduling outdoor work in the summer, investing in up-front safety training,
or choosing high-quality materials, these are examples of retaining a risk
Budget reserves are set up to cover
identified risks associated with specific segments of a project while
management reserves are set up to cover unidentified risks associated with the
total project
Change management systems involve
reporting, controlling, and recording changes to the project baseline
Enhancing a risk is a tactic that seeks to
eliminate the uncertainty associated with an opportunity to ensure that it
definitely happens
Contingency funding is made up of budget
reserves and management reserves
Resources are adequate, but demand varies
widely over the life of the project. Delaying noncritical activities to lower
peak demand on resources is known as resource
If resources are not adequate to meet peak
demands, the resulting reschedule is termed
Which of the following is NOT a potential
consequence of failing to identify limited resources before project
implementation
When developing a new software package,
logically, the software must be designed before the code is written, and the
code must be written before it is tested. These activities are dependent on
each other by ______ constraints
When considering the sequence and timing
of activities, which of the following is NOT one of the types of project
network constraints
Sam, the project engineer, has been
scheduled to run the product system test at the same time he is to build a
marketing prototype. This is an example of what type of resource constraint
Susan is to conduct environmental testing
but the chamber cannot hold all the equipment that she wants to test. This is an
example of a constraint that could impact the sequence and timing of activities
in a project network. What type of constraint is it
All of the following are types of resource
constraints EXCEPT
Gene is trying to order the concrete
needed to continue his project. However, the supplier will not be able to
deliver it until next week. This is an example of what kind of resource
constraint
A special truck that George needs on his
project has been scheduled on another project. This is an example of what type
of resource constraint?
Most of the scheduling methods available
today require the project manager to classify the project as either _____
constrained or ______ constrained
Regina's boss has told her that her
project is very important. If the critical path is delayed, she will be given
whatever she needs to get it back on schedule. Her project is classified as
______ constrained
In reviewing the status of her project
with top management, Shirley was told that there are only two programmers that
she can use for her project. Her project is classified as _______ constrained
All resource leveling techniques involve
Technical constraints have been carefully
considered when developing a project network. Which of the following is true at
this point
Rachel is working on a project that
technically allows three activities to be done at the same time. If they were
to be implemented at the same time, she would need 5 contractors in order for
the activities to be completed on time. There are only 3 available for her to
use. This is an example of what type of constraint
Resource leveling or smoothing can have
all the following results on a project EXCEPT
Jan is trying to reallocate resources in a
time-constrained project to create smoother resource utilization. She should
first identify activities with the
In a resource-constrained project, which
of the following is most likely to be changed
In a resource-constrained project, the
first priority in assigning resources is usually given to activities with the
In a resource-constrained project the
second priority in assigning resources is usually given to activities with the
Tony has realized that two activities in
his project cannot be done at the same time because not enough resources are
available. Activity 3 is critical and has a duration of 5 days. Activity 4 has
2 days of slack and a duration of 2 days. How will he decide which activity
should be scheduled first
Splitting an activity can result in all of
the following EXCEPT
All of the following are benefits of
scheduling resources before project implementation EXCEPT
These are all guidelines a project manager
should consider when assigning project work EXCEPT
When a company will reduce the number of
projects they have to manage internally to only core projects and send noncritical
projects to contractors and consulting firms this is called
Which of the following is NOT one of the
more common problems associated with scheduling multiproject resources
In a resource-constrained project the
third priority in assigning resources is usually given to activities with the
Why is it necessary to have a time-phased
budget baseline
Project budgets are developed by
time-phasing which of the following
A project budget report is showing our
project as spending $35,000 against a budgeted amount of $40,000. Which of the
following is true
Delaying noncritical activities to lower
peak demand and, thus, increase resource utilization is called resource ____
A(n) ________ constraint addresses the
sequence in which project activities must occur even after considering resource
constraints
Having one person responsible for
performing several activities, all due at the same time, is an example of a(n)
_____ constraint
Trying to renovate a ship compartment that
is too small for more than one person is an example of a(n) _____ resource
constraint
A shortage of programmers to write
software is an example of a(n) _____ type of resource constraint
The shortage of computer chips to produce
a circuit board is an example of a(n) ______ type of resource constraint
If three copiers are needed to produce a
final report on time and only two are available, the project is facing a(n)
________ type of resource constraint
Resource dependency takes priority over
the technological dependency but does not violate _____ dependencies
In order that the new product is on the
shelf for the Christmas buying season, the development of the new product would
be classified as a(n) ________ -constrained project
Beth has two engineers assigned to her
project and does not have access to more even if the result means extending the
completion date on her project. She is managing a(n) ________ -constrained
project
All leveling techniques delay noncritical
activities by using ________ to reduce peak demand
When scheduling activities in a resource-constrained
project, typically the activity scheduled first has the ______ amount of slack
Since resource leveling or smoothing
delays noncritical activities, a common result is an increase in network _____
When the work in an activity is
interrupted to work on another activity and is then resumed at a later point in
time, it is called ____
In scheduling resource-constrained
projects, _____ are typically used rather than optimum mathematical solutions
When classifying projects, ________
constrained means that project duration is fixed and resources are flexible
When classifying projects, ________
constrained means that a specific resource is fixed and the duration of the
project is flexible
Start-up and shutdown costs are major
considerations when using the ______ scheduling technique
After resource leveling or smoothing one
goal is that the amount of resources needed over the life of the project will
be
Many companies are ______ project work to
contractors and consultants as a means of dealing with the peaks and valleys of
resource allocation among projects
When a project is classified as
resource-constrained and a resource constraint exists, the project duration is
typically ____
In reality resource allocation generally
occurs in a(n) ______ environment where the demands of one project have to be
reconciled with the needs of other projects
Without a ____ budget a good project
schedule and cost control are impossible
A project cost baseline is also called
____
The fact that you must pour foundation
before you frame the house and that you have to frame the house before you can
put on the roof demonstrates scheduling constraints
Too many parallel activities for one
individual is an example of a resource constraint
The level of resources each activity will
need to be completed in the given amount of time has been estimated; therefore,
there are no resource constraints
Resource leveling or smoothing is only
used on projects which are resource constrained
Resource bottlenecks are one of the three
more common problems encountered in managing multiproject resource schedules
The inability to fit more than two earth
movers on a construction site at the same time when more are needed to complete
the activity on time is an example of a physical constraint
In a resource-constrained project, the
completion date is most likely to change.
Having too few programmers and too many
engineers is an example of a people resource constraint
If a project needs one earth mover six
months from now in order to complete one activity, and the organization has
four such machines, there is no equipment resource constraint
A lack of readily available engineers is a
technical constraint
Resource dependency takes priority over
technological dependency but it does not violate it
To determine if a project is
time-constrained or resource-constrained you would consult the project priority
matrix
Sequential activities hold just as much
potential for resource conflicts as parallel activities.
All leveling techniques delay noncritical
activities by using positive slack to smooth out the resource requirements
Since resource leveling or smoothing
delays noncritical activities, a common result is a decrease in network
sensitivity
Scheduling projects classified as
resource-constrained focuses on completing the project as soon as possible
under the given resource constraints
When resource constraints are added to
technical constraints the original project network may change as well as the
completion date
When scheduling activities in a
resource-constrained project typically the activity scheduled first has the
most amount of slack
A project budget report is showing our
project as spending $35,000 against a budgeted amount of $40,000. We can assume
that everything is going as planned and that we are under budget
Splitting is a scheduling technique used
to get a better schedule or better resource utilization and should be used
without hesitation
Without a time-phased budget a good
project schedule and cost control are impossible
If resources are truly limited and
activity time estimates are accurate, the resource-constrained schedule will
materialize as the project is implemented, not the time-constrained schedule
Project managers should always assign the
best people to the most difficult tasks
1. The president of
a software company remarks in a speech that new technologically advanced
software will be available in one year. This is an example of reducing project
duration caused by:
2.
Intense global competition and rapid technological advances create pressure on
developing projects rapidly. This is an example of reducing project duration
caused by:
3. A contractor
finished a bridge across a lake 18 months early and received more than $6
million for the early completion. This is an example of reducing project duration
caused by:
4.
Adverse weather, design flaws, and equipment breakdown can create negative
slack. This is an example of reducing project duration caused by:
5. Total project
costs include all of the following except:
6.
Which of the following is not considered a project indirect cost?
7. Project costs are
generally classified as ____ costs.
8.
Low-cost, realistic, efficient methods for completing an activity under normal
conditions are supported by ____ time.
9. The shortest
possible time an activity can be completed realistically is called ___ time.
10.
The most common response for meeting unattainable deadlines is to
11. ____ costs are
incurred when completing an activity in its realistically shortest time.
12.
An activity's crash costs include ____ costs.
13. Cost slope can
be determined by dividing the
14.
The less steep the cost slope of an activity, the
15. Which of the
following correctly calculates an activity's cost slope?
16.
An activity's cost slope represents an activity's
17. In selecting the
best activity to reduce you would first select the activity with the
18.
The optimum duration for a project is at the point where:
19. Creating a
Project Cost-Duration graph is useful:
20.
Crashing a project should occur:
21. If a network has
several critical or near-critical paths it is deemed to be:
22.
The project direct-cost line near the normal point is usually:
23. The relationship
between cost and time for various durations is assumed to be:
24.
A common method for shortening the project time is to:
25. A positive
situation where moving toward the optimum time can result in very real, large
savings—this occurs when the network is:
26.
Which of the following is/are included in a Project Cost-Duration Graph?
27. One way of
reducing project costs is identifying tasks that _________ can do themselves.
28.
The most common method for shortening project time is to
29. Which of the
following is not one of the more commonly used options for cutting
project costs?
30.
Which of the following is the most common method for shortening project time?
31. According to
Brooks' Law, adding more people to a late project is most likely to have which
of the following impact?
32.
Which of the following is the easiest method for shortening project time?
33. Which of the
following is not one of the techniques for accelerating project
completion?
34.
When the project team is salaried, which of the following is the preferred
choice for accelerating project completion?
35. The Snapshot
from Practice "Cell-Phone Wars" is an excellent example of reducing
project duration due to:
36.
When a politician makes a public statement that a new building will be
available in two years, a(n) ________ duration has reduced the project
duration.
37.
Intense global competition and rapid technological advances combine to create
a(n) ________ imposed project duration date.
38.
The Snapshot from Practice which detailed the Northridge earthquake
demonstrated the importance of reducing a project's ______.
39.
Sometimes very high ________ costs are recognized before a project begins and
reducing these costs through shorter project durations becomes a high priority.
40.
The ________ project cost is the sum of the indirect and direct costs.
41.
Costs such as supervision, administration, consultants, and interest are
examples of ________ project costs.
42.
Costs such as labor, materials, equipment, or contractors are examples of
________ project costs.
43.
Direct costs are assignable directly to a project ________.
44.
Because direct costs are assumed to be developed from normal methods and time,
any reduction in activity time should ________ the cost of the activity.
45.
To shorten the duration of a project the project manager should limit the
choices of activities to just those which ________.
46.
The ________ time for an activity represents low-costs, realistic, efficient
methods for completing the activity under typical conditions.
47.
Shortening an activity is called ________.
48.
The direct costs for completing an activity as early as possible is called its
________.
49.
An activity's ________ is calculated by dividing the rise by the run.
50.
Subtracting an activity's normal cost from the crash cost will calculate an
activity's ________.
51.
Subtracting an activity's crash time from the normal time will calculate an
activity's ________.
52.
When considering whether to move the project to its optimum cost-time position,
the manager should also consider ________.
53.
A network is considered to be ________ if it has a predominate critical path
with no other path close in terms of slack.
54.
The easiest way to add more resources to a project is not to add more people,
but to schedule ________.
55.
According to ________, adding more manpower to a late software project makes it
later.
56.
The easiest way to add more labor to a project is not to add more people, but
to add ___________.
57.
____________ is the rearranging of the project network logic so that critical
activities are done in parallel rather than sequentially.
58.
___________ is probably the most common response for meeting unattainable
deadlines.
59.
In the "I'll Bet You..." Snapshot from Practice, the draftsman won
___________ for making a very difficult deadline.
60.
A rule of thumb for moderate- to high-technology firms is that a six-month
delay in bringing a product to market can result in a gross profit loss of
about 35 percent.
61.
Imposed project durations almost always leads to a higher-cost project than one
planned with detailed scheduling of all the project's activities.
62.
Managers have several effective methods for crashing specific project
activities when resources are not constrained.
63.
Indirect costs generally represent overhead costs such as supervision,
administration, consultants, and interest.
64.
The total cost for each possible duration of a project is the sum of labor,
materials, and equipment.
65.
Direct costs are so named because they can be assigned directly to a work
package and activity.
66.
Because direct costs are assumed to be developed from normal methods and time,
any reduction in activity time should add to the costs of the activity.
67.
The sum of the costs of all the work packages represents the total direct costs
for the project.
68.
Incentive contracts can make reduction of project time rewarding—usually for
both the project contractor and owner.
69.
Shortening an activity's duration is termed crashing.
70.
Expected time for an activity represents low-cost, realistic, efficient methods
for completing the activity under anticipated conditions.
71.
Crash cost is the incremental cost incurred when an activity is reduced
in duration.
72.
The cost slope of an activity is calculated by dividing the run by the rise.
73.
Crash time is the greatest time reduction possible under realistic
conditions.
74.
The higher the slope of an activity the greater the cost to reduce its
duration.
75.
Creating a Project Cost-Duration Graph in the pre-project planning phase
without an imposed duration is the best time to use this tool.
76.
Crashing a more expensive activity may be wise if fewer inherent risks are
involved.
77.
A project network is classified as sensitive if it has a large number of
interacting paths.
78.
Collecting crash times for a moderate-size project is relatively easy.
79.
While the relationship between normal and crash times is really curvilinear,
the assumption that it is linear is seldom a concern for practicing managers.
80.
The accuracy of crash times and costs is frequently rough at best, when
compared with normal time and cost.
81.
One of the advantages of using a Project Cost-Duration Graph is that it keeps
the importance of indirect costs in the forefront of decision making.
I would highly recommend Le_ meridian funding services to any person in need financial help and they will keep you on top of high directories for any further needs. Once again I commend yourself and your staff for extraordinary service and customer service, as this is a great asset to your company and a pleasant experience to customers such as myself. Wishing you all the best for the future.Le meridian funding service is best way to get an easy loan,here is there email..lfdsloans@lemeridianfds.com Or talk to Mr Benjamin On WhatsApp Via_+1-989-394-3740 Thank You for helping me with loan once again in my sincerely heart I'm forever grateful.
ReplyDelete